1439 S BUNDY DR 90025
Certificate Information: 1439 S BUNDY DR 90025
- Application / Permit
- 19016-10000-39695
- Plan Check / Job No.
- B19LA26206
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- EPLAN 1544 - Soft-Story seismic retrofit per LABC Chapter 93: SOFT STORY SEISMIC REINFORCEMENT AT BUILDING PARKING GARAGE USING (3) SPECIAL CANTILEVERED COLUMNS WITH GRADE BEAMS.
- Permit Issued
- Issued on 9/14/2020
- Issuing Office
- Current Status
- CofC Issued on 3/16/2021
Permit Application Status History
| Submitted | 12/18/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/8/2020 | VARAND SARKISIAN |
| Corrections Issued | 1/14/2020 | VARAND SARKISIAN |
| Quality Review Completed | 1/24/2020 | HANS SANTIAGO |
| Plan Check Approved | 4/6/2020 | VARAND SARKISIAN |
| Issued | 9/14/2020 | APPLICANT |
| OK for CofC | 3/12/2021 | GRANT WOODS |
| CofC Issued | 3/16/2021 | TED RIES |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 8/21/2020 | PHILLIP MUNGUIA |
Contact Information
| Contractor | Cal - Quake Construction Inc; Lic. No.: 759817-B | 636 NORTH FORMOSA AVENUE LOS ANGELES, CA 90036 |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 743 S SIERRA VISTA AVE C ALHAMBRA, CA 91801 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/17/2020 | Not Ready for Inspection | JOHN DODGE |
| Pre-Inspection | 9/22/2020 | Not Ready for Inspection | JOHN DODGE |
| Pre-Inspection | 9/29/2020 | Approved | GRANT WOODS |
| Wood Frame | 10/6/2020 | Approved | GRANT WOODS |
| Deputy Wood Construction | 10/9/2020 | Conditional Approval | JOHN DODGE |
| Deputy Other (see comments) | 10/14/2020 | Conditional Approval | GRANT WOODS |
| Deputy Wood Construction | 10/14/2020 | Conditional Approval | GRANT WOODS |
| Excavation/Setback/Form/Re-Bar | 10/14/2020 | Approved | RUSSELL BONVOULOIR |
| Wood Frame | 11/4/2020 | Approved | RUSSELL BONVOULOIR |
| Deputy Wood Construction | 11/5/2020 | Conditional Approval | JOHN DODGE |
| Interior/Exterior Lathing | 11/13/2020 | Approved | RUSSELL BONVOULOIR |
| Final | 12/1/2020 | Corrections Issued | JOHN DODGE |
| SGSOV-Seismic Gas S/O Valve | 12/1/2020 | SGSOV Not Ready | JOHN DODGE |
| Smoke Detectors | 12/1/2020 | Not Ready for Inspection | JOHN DODGE |
| Final | 3/9/2021 | Partial Inspection | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 3/9/2021 | SGSOV Approved | GRANT WOODS |
| Smoke Detectors | 3/9/2021 | Not Ready for Inspection | GRANT WOODS |
| Final | 3/12/2021 | OK for CofC | GRANT WOODS |
| Smoke Detectors | 3/12/2021 | Approved | GRANT WOODS |