233 S BEAUDRY AVE 90012

Certificate Information: 233 S BEAUDRY AVE 90012

Application / Permit
19016-10000-39658
Plan Check / Job No.
B19LA26169
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
Tenant improvement on 11th, 12th and penthouse floors to (E) office building, including new non-bearing partitions, suspended ceiling, finishes and restrooms.
Permit Issued
Issued on 8/20/2020
Issuing Office
Metro
Current Status
Permit Finaled on 1/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/11/2019 APPLICANT
Assigned to Plan Check Engineer 12/19/2019 HELEN NGUYEN
Corrections Issued 12/23/2019 HELEN NGUYEN
Quality Review Completed 12/28/2019 YOUNG KIM
Disabled Access Plans Picked Up 1/7/2020 APPLICANT
Plan Check Approved 2/19/2020 HELEN NGUYEN
No Progress 7/1/2020 HELEN NGUYEN
Green Plans Picked Up 7/1/2020 APPLICANT
Plan Check Approved 7/22/2020 HELEN NGUYEN
Issued 8/20/2020 APPLICANT
Building Plans Picked Up 8/24/2020 APPLICANT
Permit Finaled-Status Void 11/17/2022 TIMOTHY BUXTON
Re-Activate Permit 12/21/2022 TIMOTHY BUXTON
Permit Finaled 1/11/2023 RAFAEL ESPINOZA

Permit Application Clearance Information

Green Code Cleared 1/28/2020 COLIN LOREDO
Specific Plan Cleared 1/28/2020 KEVIN ARUCAN
DAS Clearance Cleared 2/13/2020 HELEN NGUYEN
Fire Marshall Fire Life Safety Cleared 2/18/2020 WILLIAM JOHNS

Contact Information

Architect Diaz,, Osvaldo; Lic. No.: C22020 2226 PINECREST COURT      FULLERTON, CA 92831
Contractor City Constructors Inc; Lic. No.: 834591-B 3125 N BROADWAY      LOS ANGELES, CA 90031

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Drywall Nailing 11/30/2020 Partial Inspection KATY RAMIREZ
Light Gage Steel Frame 11/30/2020 Partial Inspection KATY RAMIREZ
Deputy Drilled-In Anchors 12/2/2020 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 12/2/2020 Corrections Issued KATY RAMIREZ
Deputy Drilled-In Anchors 12/3/2020 No Access for Inspection KATY RAMIREZ
Deputy Steel/Welding 12/3/2020 No Access for Inspection KATY RAMIREZ
Pre-Inspection 12/7/2020 Corrections Issued KATY RAMIREZ
Reinforced Concrete Frame 12/29/2020 Partial Approval DANIEL COLLINS
Drywall Nailing 1/8/2021 Partial Approval DANIEL COLLINS
Insulation 1/8/2021 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 1/8/2021 Conditional Approval DANIEL COLLINS
Insulation 1/20/2021 Partial Approval DANIEL COLLINS
Insulation 1/25/2021 Partial Approval DANIEL COLLINS
Drywall Nailing 2/8/2021 Corrections Issued KATY RAMIREZ
Pre-Inspection 2/26/2021 Approved KATY RAMIREZ
Drywall Nailing 3/9/2021 Partial Approval KATY RAMIREZ
Light Gage Steel Frame 3/9/2021 Partial Approval KATY RAMIREZ
T-Bar Ceiling 3/18/2021 Partial Inspection DANIEL COLLINS
Insulation 3/22/2021 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 3/22/2021 Partial Approval DANIEL COLLINS
Insulation 3/24/2021 Partial Approval DANIEL COLLINS
Drywall Nailing 4/13/2021 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 4/13/2021 Partial Approval DANIEL COLLINS
Drywall Nailing 4/21/2021 Partial Approval KATY RAMIREZ
T-Bar Ceiling 4/22/2021 Corrections Issued KATY RAMIREZ
Light Gage Steel Frame 4/27/2021 Corrections Issued KATY RAMIREZ
Drywall Nailing 4/29/2021 Partial Approval KATY RAMIREZ
Light Gage Steel Frame 5/5/2021 Partial Inspection KATY RAMIREZ
Light Gage Steel Frame 5/7/2021 Partial Inspection KATY RAMIREZ
Light Gage Steel Frame 5/24/2021 Partial Approval DANIEL COLLINS
T-Bar Ceiling 5/24/2021 Conditional Approval DANIEL COLLINS
Light Gage Steel Frame 5/27/2021 Partial Approval DANIEL COLLINS
T-Bar Ceiling 5/27/2021 Partial Approval DANIEL COLLINS
Drywall Nailing 6/17/2021 Partial Approval JONATHAN QUACH
Green Building Final 3/7/2022 Not Ready for Inspection KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 3/7/2022 SGSOV Not Ready KATY RAMIREZ
Smoke Detectors 3/7/2022 Not Ready for Inspection KATY RAMIREZ
Final 3/9/2022 Not Ready for Inspection TIMOTHY BUXTON
Green Building Final 3/9/2022 Not Ready for Inspection TIMOTHY BUXTON
SGSOV-Seismic Gas S/O Valve 3/9/2022 SGSOV No Gas TIMOTHY BUXTON
Smoke Detectors 3/9/2022 Approved TIMOTHY BUXTON
Final 7/14/2022 Conditional Approval DARRYL ARNOLD
Green Building Final 7/14/2022 Conditional Approval DARRYL ARNOLD
Final 9/2/2022 Not Ready for Inspection TIMOTHY BUXTON
Green Building Final 9/2/2022 Not Ready for Inspection TIMOTHY BUXTON
Final 11/17/2022 Conditional Approval TIMOTHY BUXTON
Green Building Final 11/17/2022 Approved TIMOTHY BUXTON