4655 N NATICK AVE BLDG 2 91403
Certificate Information: 4655 N NATICK AVE BLDG 2 91403
- Application / Permit
- 19016-10000-39604
- Plan Check / Job No.
- B19LA26124
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (35) Condo-Multi Family
- Work Description
- \SOFT STORY RETROFIT AS PER LABC CH. 93. INSTALL 14 TOTAL STEEL CANTILEVER COLUMNS.
- Permit Issued
- Issued on 1/28/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 12/11/2020
Permit Application Status History
| Submitted | 12/11/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/18/2019 | BIDYUT RATH |
| Corrections Issued | 12/23/2019 | HANS SANTIAGO |
| Quality Review Completed | 12/26/2019 | SAI KHUM |
| Building Plans Picked Up | 12/30/2019 | APPLICANT |
| Plan Check Approved | 1/24/2020 | ANDREW SANTIAGO |
| Issued | 1/28/2020 | LADBS |
| OK for CofC | 9/24/2020 | DANIEL VARNUM |
| CofC Issued | 12/11/2020 | DAVID TSAU |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 1/28/2020 | MICHAEL GREGERSON |
Contact Information
| Contractor | Elrom Construction; Lic. No.: 571666-B | 22457 VENIDO ROAD WOODLAND HILLS, CA 91364 |
| Engineer | Kiledjian,, George Zohrab; Lic. No.: C74761 | 11447 VIKING AVE NORTHRIDGE, CA 91326 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/12/2020 | Partial Approval | KENNETH ROBERTS |
| Footing/Foundation/Slab | 3/12/2020 | Partial Approval | KENNETH ROBERTS |
| Deputy Reinf. Concrete | 3/26/2020 | Approved | HAMID PISHEHVAR |
| Wood Frame | 4/1/2020 | Partial Approval | JONATHAN QUACH |
| Deputy Drilled-In Anchors | 4/7/2020 | Conditional Approval | DANIEL VARNUM |
| Deputy Steel/Welding | 4/9/2020 | Approved | HAMID PISHEHVAR |
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2020 | Partial Approval | DANIEL VARNUM |
| Footing/Foundation/Slab | 4/16/2020 | Approved | DANIEL VARNUM |
| Structural Steel Frame | 4/16/2020 | Approved | DANIEL VARNUM |
| Wood Frame | 4/16/2020 | Approved | DANIEL VARNUM |
| Deputy Reinf. Concrete | 4/17/2020 | Approved | HAMID PISHEHVAR |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2020 | Partial Approval | DANIEL VARNUM |
| Footing/Foundation/Slab | 4/30/2020 | Partial Approval | DANIEL VARNUM |
| Structural Steel Frame | 4/30/2020 | Not Ready for Inspection | DANIEL VARNUM |
| Wood Frame | 4/30/2020 | Not Ready for Inspection | DANIEL VARNUM |
| Deputy Reinf. Concrete | 5/4/2020 | Conditional Approval | DANIEL VARNUM |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2020 | Partial Approval | DANIEL VARNUM |
| Interior/Exterior Lathing | 5/5/2020 | Not Ready for Inspection | DANIEL VARNUM |
| Interior/Exterior Lathing | 5/11/2020 | Approved | DANIEL VARNUM |
| Final | 6/29/2020 | Not Ready for Inspection | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 6/29/2020 | SGSOV Not Ready | DANIEL VARNUM |
| Smoke Detectors | 6/29/2020 | Not Ready for Inspection | DANIEL VARNUM |
| Final | 9/24/2020 | OK for CofC | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 9/24/2020 | SGSOV Gas Company | DANIEL VARNUM |
| Smoke Detectors | 9/24/2020 | Approved | DANIEL VARNUM |