8828 S HAAS AVE 90047

Certificate Information: 8828 S HAAS AVE 90047

Application / Permit
19016-10000-39575
Plan Check / Job No.
B19LA26115
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Addition and conversion of existing garage to accessory dwelling unit per AB 494 and SB 229
Permit Issued
Issued on 1/10/2020
Issuing Office
South Los Angeles
Current Status
CofO Issued on 9/3/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/11/2019 APPLICANT
Assigned to Plan Check Engineer 12/11/2019 SHANGQIN XIE
Plan Check Approved 12/11/2019 SHANGQIN XIE
Issued 1/10/2020 LADBS
CofO in Progress 5/6/2020 FREDDIE RIVERA
Permit Finaled 9/3/2020 DEROLD HAUFF
CofO Issued 9/3/2020 DEROLD HAUFF
Permit Finaled 9/3/2020 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/11/2019 EMIL KYUPELYAN
Construction within easement Cleared 12/11/2019 TORI CHEN
Eng Process Fee Ord 176,300 Cleared 12/11/2019 EMIL KYUPELYAN
Roof/Waste drainage to street Cleared 12/11/2019 EMIL KYUPELYAN
Sewer availability Cleared 12/11/2019 EMIL KYUPELYAN
ZI Cleared 12/11/2019 JASON CHAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/29/2020 Partial Approval FREDDIE RIVERA
Sewer 1/29/2020 Approved FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 2/3/2020 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 2/21/2020 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 3/10/2020 Not Ready for Inspection FREDDIE RIVERA
ELECTRICAL-Rough 3/10/2020 Corrections Issued FREDDIE RIVERA
METHANE-Rough 3/10/2020 Approved FREDDIE RIVERA
PLUMBING-Rough 3/10/2020 Approved FREDDIE RIVERA
Underground Mechanical 3/10/2020 Partial Approval FREDDIE RIVERA
BUILDING-Rough-Frame 3/16/2020 Conditional Approval FREDDIE RIVERA
ELECTRICAL-Rough 3/16/2020 Approved FREDDIE RIVERA
Green Building Rough 3/16/2020 Approved FREDDIE RIVERA
HVAC-Rough 3/16/2020 Approved FREDDIE RIVERA
Interior/Exterior Lathing 3/16/2020 Partial Approval FREDDIE RIVERA
Insulation 3/19/2020 Approved SABAS ALONSO
Drywall Nailing 3/25/2020 Corrections Issued ALEJANDRO DE ARTOLA
Drywall Nailing 4/1/2020 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 4/1/2020 Approved FREDDIE RIVERA
Interior/Exterior Lathing 4/1/2020 Approved FREDDIE RIVERA
Underground Mechanical 4/1/2020 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 4/30/2020 Approved FREDDIE RIVERA
ELECTRICAL-Final 4/30/2020 Not Ready for Inspection FREDDIE RIVERA
Final 4/30/2020 Not Ready for Inspection FREDDIE RIVERA
Grounding or Bonding 4/30/2020 Not Ready for Inspection FREDDIE RIVERA
HVAC-Final 4/30/2020 Not Ready for Inspection FREDDIE RIVERA
PLUMBING-Final 4/30/2020 Not Ready for Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 4/30/2020 SGSOV Not Ready FREDDIE RIVERA
Service/Power Release 4/30/2020 Not Ready for Inspection FREDDIE RIVERA
Smoke Detectors 4/30/2020 Not Ready for Inspection FREDDIE RIVERA
ELECTRICAL-Final 5/4/2020 Not Ready for Inspection FREDDIE RIVERA
Grounding or Bonding 5/4/2020 Not Ready for Inspection FREDDIE RIVERA
HVAC-Final 5/4/2020 Corrections Issued FREDDIE RIVERA
PLUMBING-Final 5/4/2020 Approved FREDDIE RIVERA
Service/Power Release 5/4/2020 Not Ready for Inspection FREDDIE RIVERA
ELECTRICAL-Final 5/6/2020 Approved FREDDIE RIVERA
Final 5/6/2020 OK to Issue CofO FREDDIE RIVERA
Grounding or Bonding 5/6/2020 Approved FREDDIE RIVERA
HVAC-Final 5/6/2020 Approved FREDDIE RIVERA
PLUMBING-Final 5/6/2020 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 5/6/2020 SGSOV Approved FREDDIE RIVERA
Service/Power Release 5/6/2020 Approved FREDDIE RIVERA
Smoke Detectors 5/6/2020 Approved FREDDIE RIVERA