15430-15432 W MAYALL ST 91345
Certificate Information: 15430-15432 W MAYALL ST 91345
- Application / Permit
- 19016-10000-38949
- Plan Check / Job No.
- B19LA25726
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERSION OF EXISTING ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB494 & SB229
- Permit Issued
- Issued on 1/24/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 4/24/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/5/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/9/2019 | SHANGQIN XIE |
| Corrections Issued | 12/9/2019 | SHANGQIN XIE |
| Plan Check Approved | 1/13/2020 | KEVIN MORALES |
| Plan Check Approved | 1/13/2020 | CHARLES CANNING |
| Issued | 1/24/2020 | LADBS |
| CofO in Progress | 3/16/2021 | JENNIFER RABUCHIN |
| CofO Issued | 4/24/2021 | MICHAEL SMITH |
| Permit Finaled | 4/24/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 12/18/2019 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 12/18/2019 | THOMAS LANG |
| Sewer availability | Cleared | 12/18/2019 | THOMAS LANG |
Contact Information
| Contractor | Stone Depot Building & Construction; Lic. No.: 1036867-B | 977 LINDA VISTA DRIVE STE B SAN MARCOS, CA 92078 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/7/2020 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 2/7/2020 | Partial Approval | JENNIFER RABUCHIN |
| Sewer | 2/7/2020 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 2/26/2020 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 2/26/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Gas Test | 2/26/2020 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 2/26/2020 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 2/26/2020 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 3/3/2020 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 3/3/2020 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 3/17/2020 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Green Building Rough | 3/17/2020 | Not Ready for Inspection | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 3/31/2020 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 3/31/2020 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 3/31/2020 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 3/31/2020 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 3/31/2020 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Insulation | 4/8/2020 | Not Ready for Inspection | MICHAEL TEMPLE |
| Interior/Exterior Lathing | 4/8/2020 | Corrections Issued | MICHAEL TEMPLE |
| Shower Pan | 4/8/2020 | Corrections Issued | MICHAEL TEMPLE |
| BUILDING-Rough-Frame | 4/15/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Insulation | 4/15/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Shower Pan | 4/15/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Insulation | 4/17/2020 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 4/17/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Drywall Nailing | 4/28/2020 | Approved | GREGG CUMMINGS |
| Shower Pan | 4/28/2020 | Partial Approval | GREGG CUMMINGS |
| Interior/Exterior Lathing | 5/4/2020 | Partial Inspection | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 10/26/2020 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 10/26/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 10/26/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 10/26/2020 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Final | 10/26/2020 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 10/26/2020 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 10/26/2020 | Approved | JENNIFER RABUCHIN |
| Final | 11/10/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 11/10/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 11/18/2020 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Green Building Final | 11/18/2020 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Final | 12/1/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 12/1/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 1/25/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 1/25/2021 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 3/16/2021 | Approved | JENNIFER RABUCHIN |
| Final | 3/16/2021 | OK to Issue CofO | JENNIFER RABUCHIN |
| Gas Test | 3/16/2021 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 3/16/2021 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 3/16/2021 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 3/16/2021 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 3/16/2021 | Approved | JENNIFER RABUCHIN |