15430-15432 W MAYALL ST 91345

Certificate Information: 15430-15432 W MAYALL ST 91345

Application / Permit
19016-10000-38949
Plan Check / Job No.
B19LA25726
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERSION OF EXISTING ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB494 & SB229
Permit Issued
Issued on 1/24/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 4/24/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/5/2019 APPLICANT
Assigned to Plan Check Engineer 12/9/2019 SHANGQIN XIE
Corrections Issued 12/9/2019 SHANGQIN XIE
Plan Check Approved 1/13/2020 KEVIN MORALES
Plan Check Approved 1/13/2020 CHARLES CANNING
Issued 1/24/2020 LADBS
CofO in Progress 3/16/2021 JENNIFER RABUCHIN
CofO Issued 4/24/2021 MICHAEL SMITH
Permit Finaled 4/24/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 12/18/2019 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 12/18/2019 THOMAS LANG
Sewer availability Cleared 12/18/2019 THOMAS LANG

Contact Information

Contractor Stone Depot Building & Construction; Lic. No.: 1036867-B 977 LINDA VISTA DRIVE STE B      SAN MARCOS, CA 92078

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/7/2020 Approved JENNIFER RABUCHIN
PLUMBING-Rough 2/7/2020 Partial Approval JENNIFER RABUCHIN
Sewer 2/7/2020 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 2/26/2020 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 2/26/2020 Corrections Issued JENNIFER RABUCHIN
Gas Test 2/26/2020 Partial Approval JENNIFER RABUCHIN
Green Building Rough 2/26/2020 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 2/26/2020 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 3/3/2020 Corrections Issued JENNIFER RABUCHIN
HVAC-Rough 3/3/2020 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 3/17/2020 Not Ready for Inspection JENNIFER RABUCHIN
Green Building Rough 3/17/2020 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 3/31/2020 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 3/31/2020 Approved JENNIFER RABUCHIN
Green Building Rough 3/31/2020 Approved JENNIFER RABUCHIN
HVAC-Rough 3/31/2020 Approved JENNIFER RABUCHIN
Shower Pan 3/31/2020 Not Ready for Inspection JENNIFER RABUCHIN
Insulation 4/8/2020 Not Ready for Inspection MICHAEL TEMPLE
Interior/Exterior Lathing 4/8/2020 Corrections Issued MICHAEL TEMPLE
Shower Pan 4/8/2020 Corrections Issued MICHAEL TEMPLE
BUILDING-Rough-Frame 4/15/2020 Corrections Issued JENNIFER RABUCHIN
Insulation 4/15/2020 Corrections Issued JENNIFER RABUCHIN
Shower Pan 4/15/2020 Corrections Issued JENNIFER RABUCHIN
Insulation 4/17/2020 Approved JENNIFER RABUCHIN
Shower Pan 4/17/2020 Corrections Issued JENNIFER RABUCHIN
Drywall Nailing 4/28/2020 Approved GREGG CUMMINGS
Shower Pan 4/28/2020 Partial Approval GREGG CUMMINGS
Interior/Exterior Lathing 5/4/2020 Partial Inspection WILLIAM KUEHN
BUILDING-Rough-Frame 10/26/2020 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 10/26/2020 Corrections Issued JENNIFER RABUCHIN
Final 10/26/2020 Corrections Issued JENNIFER RABUCHIN
Green Building Final 10/26/2020 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 10/26/2020 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 10/26/2020 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 10/26/2020 Approved JENNIFER RABUCHIN
Final 11/10/2020 Corrections Issued JENNIFER RABUCHIN
Green Building Final 11/10/2020 Corrections Issued JENNIFER RABUCHIN
Final 11/18/2020 Not Ready for Inspection JENNIFER RABUCHIN
Green Building Final 11/18/2020 Not Ready for Inspection JENNIFER RABUCHIN
Final 12/1/2020 Corrections Issued JENNIFER RABUCHIN
Green Building Final 12/1/2020 Corrections Issued JENNIFER RABUCHIN
Final 1/25/2021 Corrections Issued JENNIFER RABUCHIN
Green Building Final 1/25/2021 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Final 3/16/2021 Approved JENNIFER RABUCHIN
Final 3/16/2021 OK to Issue CofO JENNIFER RABUCHIN
Gas Test 3/16/2021 Approved JENNIFER RABUCHIN
Green Building Final 3/16/2021 Approved JENNIFER RABUCHIN
HVAC-Final 3/16/2021 Approved JENNIFER RABUCHIN
PLUMBING-Final 3/16/2021 Approved JENNIFER RABUCHIN
Service/Power Release 3/16/2021 Approved JENNIFER RABUCHIN