11601 W BURBANK BLVD 91601
Certificate Information: 11601 W BURBANK BLVD 91601
- Application / Permit
- 19016-10000-38938
- Plan Check / Job No.
- B19LA25723
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT-STORY RETROFIT AS PER LABC CH. 93. INSTALL (3) Special Cantilever Column
- Permit Issued
- Issued on 3/3/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 1/25/2021
Permit Application Status History
| Submitted | 12/5/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/11/2019 | JESSE VIDUYA |
| Corrections Issued | 12/16/2019 | JESSE VIDUYA |
| Quality Review Completed | 12/17/2019 | SAI KHUM |
| Building Plans Picked Up | 12/19/2019 | APPLICANT |
| Plan Check Approved | 2/6/2020 | JESSE VIDUYA |
| Issued | 3/3/2020 | LADBS |
| OK for CofC | 1/22/2021 | MARK FERRARI |
| CofC Issued | 1/25/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 2/6/2020 | JASON CHAN |
| Redevelopment Project Area | Cleared | 2/6/2020 | JASON CHAN |
| Tenant Habitability Plan | Cleared | 2/27/2020 | MICHAEL GREGERSON |
Contact Information
| Contractor | Cal - Quake Construction Inc; Lic. No.: 759817-B | 636 NORTH FORMOSA AVENUE LOS ANGELES, CA 90036 |
| Engineer | Labib,, Youhanna T; Lic. No.: S4549 | 319 MAIN STREET EL SEGUNDO, CA 90245 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/7/2020 | Approved | MARK FERRARI |
| Deputy Other (see comments) | 4/24/2020 | No Access for Inspection | JOE VELASQUEZ |
| Deputy Other (see comments) | 4/29/2020 | No Access for Inspection | JOE VELASQUEZ |
| Deputy Wood Construction | 4/30/2020 | No Access for Inspection | JOE VELASQUEZ |
| Excavation/Setback/Form/Re-Bar | 5/1/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 5/1/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 5/1/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Excavation/Setback/Form/Re-Bar | 5/4/2020 | Approved | JOE VELASQUEZ |
| Deputy Reinf. Concrete | 5/7/2020 | No Access for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 5/7/2020 | Approved | JOE VELASQUEZ |
| Wood Frame | 5/7/2020 | Approved | JOE VELASQUEZ |
| Interior/Exterior Lathing | 5/22/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Interior/Exterior Lathing | 6/16/2020 | Approved | JOE VELASQUEZ |
| Final | 8/11/2020 | Corrections Issued | VAHE KELEDJIAN |
| SGSOV-Seismic Gas S/O Valve | 8/11/2020 | SGSOV Approved | VAHE KELEDJIAN |
| Smoke Detectors | 8/11/2020 | Approved | VAHE KELEDJIAN |
| Final | 12/21/2020 | Partial Approval | DANIEL VARNUM |
| Final | 1/22/2021 | OK for CofC | MARK FERRARI |