6100 W FRANKLIN AVE 90028

Certificate Information: 6100 W FRANKLIN AVE 90028

Application / Permit
19016-10000-38835
Plan Check / Job No.
B19LA25640
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
CHANGE OF USE FROM AUTO REPAIR GARAGE TO RETAIL.
Permit Issued
Issued on 9/29/2023
Issuing Office
Valley
Current Status
CofO Issued on 10/1/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/4/2019 APPLICANT
Assigned to Plan Check Engineer 12/12/2019 ARSALAN SHABESTARI
Corrections Issued 12/16/2019 ARSALAN SHABESTARI
Quality Review Completed 12/21/2019 YOUNG KIM
Building Plans Picked Up 1/3/2020 APPLICANT
Disabled Access Plans Picked Up 9/10/2020 APPLICANT
Applicant returned to address corrections 10/9/2020 ARSALAN SHABESTARI
Plan Check Approved 9/27/2023 NGHI SU
Issued 9/29/2023 APPLICANT
Permit Finaled 10/1/2025 ERNESTO CORRAL
CofO Issued 10/1/2025 ERNESTO CORRAL
Permit Finaled 10/1/2025 ERNESTO CORRAL

Permit Application Clearance Information

ZA Case Cleared 7/27/2023 SPENCER WEJROWSKI
ZA Case Cleared 7/27/2023 SPENCER WEJROWSKI
ZA Case Cleared 7/27/2023 SPENCER WEJROWSKI
Miscellaneous Cleared 8/25/2023 MAXFIELD VERMY
DAS Clearance Cleared 9/6/2023 EDDIE GARIN
Eng Process Fee Ord 176,300 Cleared 9/7/2023 JEANIE LAM
Sewer availability Cleared 9/7/2023 JEANIE LAM
Food Service Establishment Cleared 9/19/2023 BOGDAN SERBANESCU
Food establishment approval Cleared 9/27/2023 LACDHS APPROVED

Contact Information

Contractor T L M One, Inc; Lic. No.: 761755-B 909 N ALAMEDA STREET      COMPTON, CA 90220
Engineer Ghaderi,, Nader; Lic. No.: C36475 28405 SAND CANYON ROAD STE B      CANYON COUNTRY, CA 91387

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/4/2023 Corrections Issued GREGORY POMISH
Footing/Foundation/Slab 12/13/2023 Partial Approval RONALD JIMENEZ
Light Gage Steel Frame 12/22/2023 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 1/25/2024 Corrections Issued RAFAEL CORTES
Wood Frame 2/7/2024 Approved GREGORY POMISH
Insulation 2/8/2024 Approved GREGORY POMISH
Interior/Exterior Lathing 2/8/2024 Approved GREGORY POMISH
Drywall Nailing 2/13/2024 Partial Approval GREGORY POMISH
Footing/Foundation/Slab 6/3/2024 Corrections Issued TIMOTHY POWELL
Wood Frame 7/17/2024 Not Ready for Inspection TIMOTHY POWELL
Footing/Foundation/Slab 7/19/2024 Partial Approval TIMOTHY POWELL
Wood Frame 7/19/2024 Not Ready for Inspection TIMOTHY POWELL
Light Gage Steel Frame 7/26/2024 Partial Approval RAFAEL CORTES
Wood Frame 9/6/2024 Partial Inspection TIMOTHY POWELL
Wood Frame 10/18/2024 Partial Inspection LUIS CCAMACHO
Partition/T-Bar Ceiling 3/4/2025 Partial Inspection TIMOTHY POWELL
Deputy Drilled-In Anchors 3/18/2025 Partial Approval CHRISTOPHER BLACKWOOD
Footing/Foundation/Slab 3/18/2025 Partial Approval CHRISTOPHER BLACKWOOD
Footing/Foundation/Slab 4/10/2025 Conditional Approval MARTIN TAVITIAN
Final 4/24/2025 Not Ready for Inspection MARTIN TAVITIAN
Partition/T-Bar Ceiling 4/24/2025 Approved MARTIN TAVITIAN
SGSOV-Seismic Gas S/O Valve 4/24/2025 SGSOV Not Ready MARTIN TAVITIAN
Smoke Detectors 4/24/2025 Partial Approval MARTIN TAVITIAN
Final 8/1/2025 Not Ready for Inspection LUIS CCAMACHO
SGSOV-Seismic Gas S/O Valve 8/1/2025 SGSOV Not Ready LUIS CCAMACHO
Smoke Detectors 8/1/2025 Approved LUIS CCAMACHO
Final 8/14/2025 Not Ready for Inspection TIMOTHY POWELL
SGSOV-Seismic Gas S/O Valve 8/14/2025 SGSOV Approved TIMOTHY POWELL
Final 8/21/2025 Partial Inspection LUIS CCAMACHO
Final 8/29/2025 Conditional Approval RAFAEL CORTES