5164-5172 N COLUMBUS AVE 91403
Certificate Information: 5164-5172 N COLUMBUS AVE 91403
- Application / Permit
- 19016-10000-38718
- Plan Check / Job No.
- B19LA25556
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT-STORY RETROFIT AS PER LABC CH. 93. INSTALL ONE (1) STORNG WSW (SIMPSON STRONG TIE), AND ONE (1) PLYWOOD SHEAR WALL.
- Permit Issued
- Issued on 9/18/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 3/18/2022
Permit Application Status History
| Submitted | 12/3/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/18/2019 | BIDYUT RATH |
| Corrections Issued | 12/30/2019 | BIDYUT RATH |
| Quality Review Completed | 12/31/2019 | SAI KHUM |
| Building Plans Picked Up | 1/13/2020 | APPLICANT |
| Applicant returned to address corrections | 1/30/2020 | BIDYUT RATH |
| Applicant returned to address corrections | 2/12/2020 | BIDYUT RATH |
| Plan Check Approved | 2/24/2020 | BIDYUT RATH |
| Issued | 9/18/2020 | APPLICANT |
| OK for CofC | 3/11/2022 | KENNETH ROBERTS |
| CofC Issued | 3/18/2022 | HENRY BAGHDASSARIAN |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 9/15/2020 | STEVEN HOFSTAD |
Contact Information
| Contractor | Cohen Construction Co Inc; Lic. No.: 962357-B | 1306 N SYCAMORE AVE LOS ANGELES, CA 90028 |
| Engineer | Chu,, James; Lic. No.: S1436 | 2425 WESTRIDGE RD LOS ANGELES, CA 90049 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/19/2020 | Partial Inspection | DANIEL VARNUM |
| Footing/Foundation/Slab | 11/6/2020 | Not Ready for Inspection | DANIEL VARNUM |
| Wood Frame | 11/6/2020 | Partial Approval | DANIEL VARNUM |
| Deputy Wood Construction | 11/13/2020 | Conditional Approval | DANIEL VARNUM |
| Footing/Foundation/Slab | 11/13/2020 | Not Ready for Inspection | DANIEL VARNUM |
| Insulation | 11/13/2020 | Approved | DANIEL VARNUM |
| Wood Frame | 11/13/2020 | Partial Approval | DANIEL VARNUM |
| Footing/Foundation/Slab | 11/17/2020 | Partial Approval | DANIEL VARNUM |
| Interior/Exterior Lathing | 11/17/2020 | Partial Approval | DANIEL VARNUM |
| Wood Frame | 11/17/2020 | Not Ready for Inspection | DANIEL VARNUM |
| Deputy Reinf. Concrete | 11/20/2020 | Conditional Approval | DANIEL VARNUM |
| Interior/Exterior Lathing | 11/23/2020 | Not Ready for Inspection | DANIEL VARNUM |
| Wood Frame | 11/23/2020 | Partial Approval | DANIEL VARNUM |
| Wood Frame | 12/2/2020 | Partial Approval | DANIEL VARNUM |
| Wood Frame | 12/10/2020 | Partial Inspection | DANIEL VARNUM |
| Wood Frame | 1/5/2021 | Approved | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 1/13/2021 | SGSOV Not Ready | DANIEL VARNUM |
| Final | 2/18/2021 | Corrections Issued | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 2/18/2021 | SGSOV Not Ready | DANIEL VARNUM |
| Smoke Detectors | 2/18/2021 | Approved | DANIEL VARNUM |
| Final | 3/9/2022 | Not Ready for Inspection | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 3/9/2022 | SGSOV Approved | KENNETH ROBERTS |
| Final | 3/11/2022 | OK for CofC | KENNETH ROBERTS |