5164-5172 N COLUMBUS AVE 91403

Certificate Information: 5164-5172 N COLUMBUS AVE 91403

Application / Permit
19016-10000-38718
Plan Check / Job No.
B19LA25556
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT-STORY RETROFIT AS PER LABC CH. 93. INSTALL ONE (1) STORNG WSW (SIMPSON STRONG TIE), AND ONE (1) PLYWOOD SHEAR WALL.
Permit Issued
Issued on 9/18/2020
Issuing Office
Metro
Current Status
CofC Issued on 3/18/2022

Permit Application Status History

Submitted 12/3/2019 APPLICANT
Assigned to Plan Check Engineer 12/18/2019 BIDYUT RATH
Corrections Issued 12/30/2019 BIDYUT RATH
Quality Review Completed 12/31/2019 SAI KHUM
Building Plans Picked Up 1/13/2020 APPLICANT
Applicant returned to address corrections 1/30/2020 BIDYUT RATH
Applicant returned to address corrections 2/12/2020 BIDYUT RATH
Plan Check Approved 2/24/2020 BIDYUT RATH
Issued 9/18/2020 APPLICANT
OK for CofC 3/11/2022 KENNETH ROBERTS
CofC Issued 3/18/2022 HENRY BAGHDASSARIAN

Permit Application Clearance Information

Tenant Habitability Plan Cleared 9/15/2020 STEVEN HOFSTAD

Contact Information

Contractor Cohen Construction Co Inc; Lic. No.: 962357-B 1306 N SYCAMORE AVE      LOS ANGELES, CA 90028
Engineer Chu,, James; Lic. No.: S1436 2425 WESTRIDGE RD      LOS ANGELES, CA 90049

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/19/2020 Partial Inspection DANIEL VARNUM
Footing/Foundation/Slab 11/6/2020 Not Ready for Inspection DANIEL VARNUM
Wood Frame 11/6/2020 Partial Approval DANIEL VARNUM
Deputy Wood Construction 11/13/2020 Conditional Approval DANIEL VARNUM
Footing/Foundation/Slab 11/13/2020 Not Ready for Inspection DANIEL VARNUM
Insulation 11/13/2020 Approved DANIEL VARNUM
Wood Frame 11/13/2020 Partial Approval DANIEL VARNUM
Footing/Foundation/Slab 11/17/2020 Partial Approval DANIEL VARNUM
Interior/Exterior Lathing 11/17/2020 Partial Approval DANIEL VARNUM
Wood Frame 11/17/2020 Not Ready for Inspection DANIEL VARNUM
Deputy Reinf. Concrete 11/20/2020 Conditional Approval DANIEL VARNUM
Interior/Exterior Lathing 11/23/2020 Not Ready for Inspection DANIEL VARNUM
Wood Frame 11/23/2020 Partial Approval DANIEL VARNUM
Wood Frame 12/2/2020 Partial Approval DANIEL VARNUM
Wood Frame 12/10/2020 Partial Inspection DANIEL VARNUM
Wood Frame 1/5/2021 Approved DANIEL VARNUM
SGSOV-Seismic Gas S/O Valve 1/13/2021 SGSOV Not Ready DANIEL VARNUM
Final 2/18/2021 Corrections Issued DANIEL VARNUM
SGSOV-Seismic Gas S/O Valve 2/18/2021 SGSOV Not Ready DANIEL VARNUM
Smoke Detectors 2/18/2021 Approved DANIEL VARNUM
Final 3/9/2022 Not Ready for Inspection KENNETH ROBERTS
SGSOV-Seismic Gas S/O Valve 3/9/2022 SGSOV Approved KENNETH ROBERTS
Final 3/11/2022 OK for CofC KENNETH ROBERTS