424 N AVENUE 56 90042

Certificate Information: 424 N AVENUE 56 90042

Application / Permit
19016-10000-38694
Plan Check / Job No.
B19LA25532
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT-STORY RETROFIT AS PER LABC CH. 93. INSTALL (1) OMF, AND (2) SCCS.
Permit Issued
Issued on 12/21/2020
Issuing Office
Current Status
CofC Issued on 5/11/2021

Permit Application Status History

Submitted 12/3/2019 APPLICANT
Assigned to Plan Check Engineer 12/18/2019 BIDYUT RATH
Corrections Issued 12/31/2019 BIDYUT RATH
Quality Review Completed 1/3/2020 SAI KHUM
Building Plans Picked Up 1/8/2020 APPLICANT
Applicant returned to address corrections 8/6/2020 BIDYUT RATH
Plan Check Approved 8/28/2020 BIDYUT RATH
Issued 12/21/2020 APPLICANT
OK for CofC 4/6/2021 MARK FERRARI
CofC Issued 5/11/2021 ERNESTO CORRAL

Permit Application Clearance Information

HPOZ Cleared 10/6/2020 JOE LUCKEY
Tenant Habitability Plan Cleared 11/25/2020 STEVEN HOFSTAD

Contact Information

Contractor K N D Construction Inc; Lic. No.: 969756-B 145 S GLENOAKS BLVD #204      BURBANK, CA 91502
Engineer Shah,, Satish Sobhagchand; Lic. No.: C56112 7611 BLACK STAR LN      LA PALMA, CA 90623

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/19/2021 Approved MARK FERRARI
Deputy Steel/Welding 2/2/2021 Conditional Approval MARK FERRARI
Deputy Drilled-In Anchors 2/16/2021 Conditional Approval MARK FERRARI
Deputy Reinf. Concrete 2/17/2021 Conditional Approval MARK FERRARI
Deputy Drilled-In Anchors 2/24/2021 Conditional Approval MARK FERRARI
Deputy Reinf. Concrete 2/24/2021 Conditional Approval MARK FERRARI
Footing/Foundation/Slab 2/25/2021 Approved MARK FERRARI
Structural Steel Frame 2/25/2021 Partial Approval MARK FERRARI
Wood Frame 2/25/2021 Partial Approval MARK FERRARI
Deputy Reinf. Concrete 2/26/2021 Conditional Approval MARK FERRARI
Deputy Wood Construction 3/5/2021 Approved MARK FERRARI
Floor/Roof Diaphrgm/Shear Wall 3/5/2021 Approved MARK FERRARI
Wood Frame 3/5/2021 Approved MARK FERRARI
Drywall Nailing 3/15/2021 Approved MARK FERRARI
Interior/Exterior Lathing 3/15/2021 Approved MARK FERRARI
Final 4/6/2021 OK for CofC MARK FERRARI
SGSOV-Seismic Gas S/O Valve 4/6/2021 SGSOV Approved MARK FERRARI
Smoke Detectors 4/6/2021 Approved MARK FERRARI