110 E 9TH ST 11TH FL--13TH FL 90015

Certificate Information: 110 E 9TH ST 11TH FL--13TH FL 90015

Application / Permit
19016-10000-38486
Plan Check / Job No.
B19LA25370
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
NON-STRUCTURAL TENANT IMPROVEMENT FOR COMMERCIAL OFFICE (TOTAL 3-FLOORS). WORK INLCUDES MINOR INTERIOR DEMOLITION, INTERIOR PATITIONS, SUSPEND CEILINGS, FINISHES, AND MILLWORK. NO CHANGE IN EXISTING USE OR OCCUPANCY
Permit Issued
Issued on 2/20/2020
Issuing Office
Metro
Current Status
Permit Finaled on 9/24/2020

Permit Application Status History

Submitted 12/2/2019 APPLICANT
Assigned to Plan Check Engineer 12/5/2019 MICHAEL LOPEZ
Corrections Issued 12/17/2019 MICHAEL LOPEZ
Quality Review Completed 12/28/2019 STANLEY RAAP
Disabled Access Plans Picked Up 1/2/2020 APPLICANT
Green Plans Picked Up 1/3/2020 APPLICANT
Building Plans Picked Up 1/8/2020 APPLICANT
Applicant returned to address corrections 1/30/2020 MICHAEL LOPEZ
Plan Check Approved 2/20/2020 MICHAEL LOPEZ
Issued 2/20/2020 LADBS
Permit Finaled 9/24/2020 KATY RAMIREZ

Permit Application Clearance Information

Green Code Cleared 1/30/2020 COLIN LOREDO
DAS Clearance Cleared 2/11/2020 WAI LAU
Fire Marshall Fire Life Safety Cleared 2/18/2020 MICHAEL LOPEZ

Contact Information

Architect Nolan,, Michael E; Lic. No.: C27606 421 WEST MELROSE STREET UNIT 8C      CHICAGO, IL 60657
Contractor Clune Construction Company L P; Lic. No.: 732107-B 350 SOUTH GRAND AVE #1600      LOS ANGELES, CA 90071

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 2/27/2020 Off-Hour Fees Due
Light Gage Steel Frame 2/27/2020 Partial Approval JONATHAN QUACH
Drywall Nailing 2/28/2020 Off-Hour Fees Due
Light Gage Steel Frame 2/28/2020 Off-Hour Fees Due
Drywall Nailing 3/3/2020 Off-Hour Fees Due
Drywall Nailing 3/3/2020 Partial Approval RONALD PACHECO
Drywall Nailing 3/6/2020 Partial Approval FRED WOHLFARTH
Drywall Nailing 3/9/2020 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 3/9/2020 Partial Approval DANIEL COLLINS
Structural Steel Frame 3/12/2020 Partial Approval JONATHAN QUACH
Drywall Nailing 3/14/2020 Partial Approval JONATHAN QUACH
Drywall Nailing 3/17/2020 Off-Hour Fees Due
T-Bar Ceiling 4/7/2020 No Access for Inspection KATY RAMIREZ
T-Bar Ceiling 4/14/2020 Partial Inspection KATY RAMIREZ
Light Gage Steel Frame 4/15/2020 Partial Approval KATY RAMIREZ
T-Bar Ceiling 4/15/2020 Corrections Issued KATY RAMIREZ
Light Gage Steel Frame 4/16/2020 Partial Inspection KATY RAMIREZ
Light Gage Steel Frame 4/17/2020 Partial Inspection KATY RAMIREZ
Drywall Nailing 4/20/2020 No Access for Inspection KATY RAMIREZ
T-Bar Ceiling 4/20/2020 No Access for Inspection KATY RAMIREZ
Light Gage Steel Frame 4/22/2020 Partial Inspection KATY RAMIREZ
T-Bar Ceiling 4/22/2020 Not Ready for Inspection KATY RAMIREZ
Light Gage Steel Frame 4/23/2020 Partial Inspection KATY RAMIREZ
T-Bar Ceiling 4/23/2020 Not Ready for Inspection KATY RAMIREZ
Drywall Nailing 4/24/2020 Partial Approval KATY RAMIREZ
T-Bar Ceiling 4/24/2020 Partial Approval KATY RAMIREZ
Drywall Nailing 4/28/2020 Partial Approval TIMOTHY BUXTON
Light Gage Steel Frame 4/28/2020 Partial Approval TIMOTHY BUXTON
T-Bar Ceiling 4/28/2020 Partial Approval TIMOTHY BUXTON
Drywall Nailing 4/29/2020 Partial Approval RONALD PACHECO
T-Bar Ceiling 4/29/2020 Not Ready for Inspection RONALD PACHECO
T-Bar Ceiling 5/1/2020 Not Ready for Inspection JONATHAN QUACH
Drywall Nailing 5/4/2020 Partial Approval DANIEL COLLINS
T-Bar Ceiling 5/4/2020 Partial Approval DANIEL COLLINS
Drywall Nailing 5/6/2020 Partial Approval JONATHAN QUACH
T-Bar Ceiling 5/6/2020 Not Ready for Inspection JONATHAN QUACH
Drywall Nailing 5/7/2020 Not Ready for Inspection JONATHAN QUACH
Pre-Inspection 5/7/2020 Partial Approval JONATHAN QUACH
Drywall Nailing 5/8/2020 Not Ready for Inspection JONATHAN QUACH
T-Bar Ceiling 5/8/2020 Not Ready for Inspection JONATHAN QUACH
Drywall Nailing 5/12/2020 Partial Approval JONATHAN QUACH
Light Gage Steel Frame 5/12/2020 Partial Approval JONATHAN QUACH
Light Gage Steel Frame 5/13/2020 Partial Approval KATY RAMIREZ
T-Bar Ceiling 5/13/2020 Not Ready for Inspection KATY RAMIREZ
Drywall Nailing 5/14/2020 Partial Inspection KATY RAMIREZ
T-Bar Ceiling 5/14/2020 Not Ready for Inspection KATY RAMIREZ
Drywall Nailing 5/15/2020 Partial Approval KATY RAMIREZ
Green Building Rough 5/18/2020 Partial Approval KATY RAMIREZ
Drywall Nailing 5/20/2020 No Access for Inspection KATY RAMIREZ
Special/Order Compliance 5/21/2020 No Access for Inspection KATY RAMIREZ
Special/Order Compliance 5/29/2020 Partial Inspection KATY RAMIREZ
Special/Order Compliance 6/4/2020 Partial Inspection KATY RAMIREZ
Pre-Inspection 6/16/2020 Partial Approval KATY RAMIREZ
Green Building Final 6/30/2020 Conditional Approval LANNY MERRICK
Special/Order Compliance 7/7/2020 Partial Inspection KATY RAMIREZ
Light Gage Steel Frame 7/8/2020 Partial Approval KATY RAMIREZ
Drywall Nailing 7/9/2020 Approved KATY RAMIREZ
Special/Order Compliance 7/10/2020 No Access for Inspection KATY RAMIREZ
Drywall Nailing 7/13/2020 Partial Approval KATY RAMIREZ
Final 7/13/2020 Not Ready for Inspection KATY RAMIREZ
Green Building Final 7/13/2020 Not Ready for Inspection KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 7/13/2020 SGSOV No Gas KATY RAMIREZ
Smoke Detectors 7/13/2020 Not Ready for Inspection KATY RAMIREZ
Special/Order Compliance 7/14/2020 Not Ready for Inspection KATY RAMIREZ
Final 9/15/2020 Not Ready for Inspection KATY RAMIREZ
Green Building Final 9/15/2020 Approved KATY RAMIREZ
Smoke Detectors 9/15/2020 Approved KATY RAMIREZ
Final 9/24/2020 Permit Finaled KATY RAMIREZ