1462 N PLAY GROUND ST 90033
Certificate Information: 1462 N PLAY GROUND ST 90033
- Application / Permit
- 19016-10000-38428
- Plan Check / Job No.
- B19LA25318
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- EPLAN 1458 - SOFT STORY RETROFIT PER LABC CHAPTER 93. INSTALL STEEL CANTILEVER COLUMNS
- Permit Issued
- Issued on 10/21/2020
- Issuing Office
- Current Status
- CofC Issued on 2/3/2022
Permit Application Status History
| Submitted | 12/12/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/2/2020 | VARAND SARKISIAN |
| Corrections Issued | 1/8/2020 | VARAND SARKISIAN |
| Quality Review Completed | 1/12/2020 | HANS SANTIAGO |
| Applicant returned to address corrections | 6/1/2020 | VARAND SARKISIAN |
| Plan Check Approved | 6/15/2020 | VARAND SARKISIAN |
| Issued | 10/21/2020 | APPLICANT |
| OK for CofC | 2/2/2022 | BRUCE CAMPBELL |
| CofC Issued | 2/3/2022 | WINSTON DUNNING |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 2/18/2020 | MICAELA TORRES-GIL |
| Redevelopment Project Area | Cleared | 2/18/2020 | MICAELA TORRES-GIL |
| Tenant Habitability Plan | Cleared | 6/29/2020 | STEVEN HOFSTAD |
Contact Information
| Contractor | Biayna Corp; Lic. No.: 998853-B | 9751 WHEATLAND AVE SUNLAND, CA 91040 |
| Engineer | Muradyan,, David; Lic. No.: S6232 | 10233 JOHANNA AVE SUNLAND, CA 91040 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/29/2021 | Approved | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 6/22/2021 | Approved | MARK FERRARI |
| Excavation/Setback/Form/Re-Bar | 6/22/2021 | Approved | MARK FERRARI |
| Wood Frame | 6/22/2021 | Partial Inspection | MARK FERRARI |
| Structural Steel Frame | 8/23/2021 | Approved | MARK FERRARI |
| Wood Frame | 8/23/2021 | Approved | MARK FERRARI |
| Interior/Exterior Lathing | 9/3/2021 | Corrections Issued | BRUCE CAMPBELL |
| SGSOV-Seismic Gas S/O Valve | 1/31/2022 | SGSOV Not Ready | BRUCE CAMPBELL |
| Final | 2/2/2022 | OK for CofC | BRUCE CAMPBELL |
| SGSOV-Seismic Gas S/O Valve | 2/2/2022 | SGSOV Approved | BRUCE CAMPBELL |
| Smoke Detectors | 2/2/2022 | Approved | BRUCE CAMPBELL |