753 N HUDSON AVE 90038
Certificate Information: 753 N HUDSON AVE 90038
- Application / Permit
- 19016-10000-38412
- Plan Check / Job No.
- B19LA25316
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LABC CHAPTER 93. INSTALL (4) FOUR SCCS, AND PLYWOOD SHEAR WALL.
- Permit Issued
- Issued on 5/6/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 1/11/2021
Permit Application Status History
| Submitted | 11/27/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/18/2019 | BIDYUT RATH |
| Corrections Issued | 12/26/2019 | BIDYUT RATH |
| Quality Review Completed | 12/27/2019 | SAI KHUM |
| Building Plans Picked Up | 1/16/2020 | APPLICANT |
| Applicant returned to address corrections | 2/25/2020 | BIDYUT RATH |
| Plan Check Approved | 2/25/2020 | BIDYUT RATH |
| Issued | 5/6/2020 | LADBS |
| OK for CofC | 1/7/2021 | MARK FERRARI |
| CofC Issued | 1/11/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 3/12/2020 | PHILLIP MUNGUIA |
Contact Information
| Contractor | D And M General Constructor Inc; Lic. No.: 745510-B | 6520 PLATT AVE #551 WEST HILLS, CA 91307 |
| Engineer | Liu,, Tienkuang; Lic. No.: C40889 | 4852 RIO HONDO AVE TEMPLE CITY, CA 91780 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/26/2020 | Corrections Issued | MARK FERRARI |
| Pre-Inspection | 6/30/2020 | Conditional Approval | MARK FERRARI |
| Wood Frame | 7/29/2020 | Partial Approval | MARK FERRARI |
| Footing/Foundation/Slab | 8/4/2020 | Not Ready for Inspection | VAHE KELEDJIAN |
| Footing/Foundation/Slab | 8/5/2020 | Partial Approval | VAHE KELEDJIAN |
| Footing/Foundation/Slab | 8/7/2020 | Approved | MARK FERRARI |
| Deputy Wood Construction | 8/19/2020 | Conditional Approval | MARK FERRARI |
| Wood Frame | 8/19/2020 | Not Ready for Inspection | MARK FERRARI |
| Structural Steel Frame | 8/24/2020 | Approved | MARK FERRARI |
| Wood Frame | 8/24/2020 | Approved | MARK FERRARI |
| Interior/Exterior Lathing | 9/23/2020 | Approved | TIMOTHY BUXTON |
| Final | 10/19/2020 | Not Ready for Inspection | JONATHAN QUACH |
| METHANE-Final | 10/19/2020 | Approved | JONATHAN QUACH |
| SGSOV-Seismic Gas S/O Valve | 10/19/2020 | SGSOV Approved | JONATHAN QUACH |
| Smoke Detectors | 10/19/2020 | Approved | JONATHAN QUACH |
| Final | 11/6/2020 | Conditional Approval | JONATHAN QUACH |
| Final | 1/7/2021 | OK for CofC | MARK FERRARI |