753 N HUDSON AVE 90038

Certificate Information: 753 N HUDSON AVE 90038

Application / Permit
19016-10000-38412
Plan Check / Job No.
B19LA25316
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT PER LABC CHAPTER 93. INSTALL (4) FOUR SCCS, AND PLYWOOD SHEAR WALL.
Permit Issued
Issued on 5/6/2020
Issuing Office
Metro
Current Status
CofC Issued on 1/11/2021

Permit Application Status History

Submitted 11/27/2019 APPLICANT
Assigned to Plan Check Engineer 12/18/2019 BIDYUT RATH
Corrections Issued 12/26/2019 BIDYUT RATH
Quality Review Completed 12/27/2019 SAI KHUM
Building Plans Picked Up 1/16/2020 APPLICANT
Applicant returned to address corrections 2/25/2020 BIDYUT RATH
Plan Check Approved 2/25/2020 BIDYUT RATH
Issued 5/6/2020 LADBS
OK for CofC 1/7/2021 MARK FERRARI
CofC Issued 1/11/2021 ERNESTO CORRAL

Permit Application Clearance Information

Tenant Habitability Plan Cleared 3/12/2020 PHILLIP MUNGUIA

Contact Information

Contractor D And M General Constructor Inc; Lic. No.: 745510-B 6520 PLATT AVE #551      WEST HILLS, CA 91307
Engineer Liu,, Tienkuang; Lic. No.: C40889 4852 RIO HONDO AVE      TEMPLE CITY, CA 91780

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/26/2020 Corrections Issued MARK FERRARI
Pre-Inspection 6/30/2020 Conditional Approval MARK FERRARI
Wood Frame 7/29/2020 Partial Approval MARK FERRARI
Footing/Foundation/Slab 8/4/2020 Not Ready for Inspection VAHE KELEDJIAN
Footing/Foundation/Slab 8/5/2020 Partial Approval VAHE KELEDJIAN
Footing/Foundation/Slab 8/7/2020 Approved MARK FERRARI
Deputy Wood Construction 8/19/2020 Conditional Approval MARK FERRARI
Wood Frame 8/19/2020 Not Ready for Inspection MARK FERRARI
Structural Steel Frame 8/24/2020 Approved MARK FERRARI
Wood Frame 8/24/2020 Approved MARK FERRARI
Interior/Exterior Lathing 9/23/2020 Approved TIMOTHY BUXTON
Final 10/19/2020 Not Ready for Inspection JONATHAN QUACH
METHANE-Final 10/19/2020 Approved JONATHAN QUACH
SGSOV-Seismic Gas S/O Valve 10/19/2020 SGSOV Approved JONATHAN QUACH
Smoke Detectors 10/19/2020 Approved JONATHAN QUACH
Final 11/6/2020 Conditional Approval JONATHAN QUACH
Final 1/7/2021 OK for CofC MARK FERRARI