7619 W BEVERLY BLVD 90036
Certificate Information: 7619 W BEVERLY BLVD 90036
- Application / Permit
- 19016-10000-38386
- Plan Check / Job No.
- B19LA25302
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Beauty Shop or Parlor
- Work Description
- CHANGE OF USE FROM RETAIL TO HAIR SALON. REMOVE AND REPLACE STAIRS TO MEZZANINE AND REMODEL BATHROOM.
- Permit Issued
- Issued on 1/31/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/11/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/27/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/5/2019 | KEVIN MORALES |
| Corrections Issued | 12/9/2019 | KEVIN MORALES |
| Quality Review Completed | 12/14/2019 | YOUNG KIM |
| Disabled Access Plans Picked Up | 12/18/2019 | APPLICANT |
| Building Plans Picked Up | 12/31/2019 | APPLICANT |
| Plan Check Approved | 1/27/2020 | KEVIN MORALES |
| Issued | 1/31/2020 | LADBS |
| CofO in Progress | 8/3/2020 | TIMOTHY BUXTON |
| CofO Issued | 8/11/2020 | ERNESTO CORRAL |
| Permit Finaled | 8/11/2020 | ERNESTO CORRAL |
Permit Application Clearance Information
| Comm Cor/Mini-Mall | Cleared | 1/3/2020 | SOPHIE GABEL-SCHEINBAU |
| Comm Cor/Mini-Mall | Cleared | 1/3/2020 | SOPHIE GABEL-SCHEINBAU |
| Eng Process Fee Ord 176,300 | Cleared | 1/3/2020 | THOMAS LANG |
| Sewer availability | Cleared | 1/3/2020 | THOMAS LANG |
| DAS Clearance | Cleared | 1/23/2020 | CHOI YAN |
Contact Information
| Architect | Gubel,, Gustavo A; Lic. No.: C26190 | 5455 WILSHIRE BLVD #1013 LOS ANGELES, CA 90036 |
| Contractor | All American Mechanical Plumbing; Lic. No.: 610554-B | 79-405 HWY111 STE 9 #422 LA QUINTA, CA 92253 |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | , |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/18/2020 | Partial Approval | JONATHAN QUACH |
| Footing/Foundation/Slab | 2/18/2020 | Not Ready for Inspection | JONATHAN QUACH |
| Drywall Nailing | 2/27/2020 | Not Ready for Inspection | JONATHAN QUACH |
| Wood Frame | 2/27/2020 | Corrections Issued | JONATHAN QUACH |
| Footing/Foundation/Slab | 3/2/2020 | Approved | TIMOTHY BUXTON |
| Wood Frame | 3/2/2020 | Partial Approval | TIMOTHY BUXTON |
| Structural Steel Frame | 3/12/2020 | Approved | TIMOTHY BUXTON |
| Wood Frame | 3/12/2020 | Approved | TIMOTHY BUXTON |
| Drywall Nailing | 4/10/2020 | Approved | TIMOTHY BUXTON |
| METHANE-Final | 5/14/2020 | Approved | TIMOTHY BUXTON |
| METHANE-Rough | 5/14/2020 | Approved | TIMOTHY BUXTON |
| Pre-Inspection | 5/14/2020 | Approved | TIMOTHY BUXTON |
| Reinforced Masonry Frame | 5/14/2020 | Approved | TIMOTHY BUXTON |
| SGSOV-Seismic Gas S/O Valve | 5/14/2020 | SGSOV Approved | TIMOTHY BUXTON |
| Smoke Detectors | 5/14/2020 | Approved | TIMOTHY BUXTON |
| Final | 7/15/2020 | Conditional Approval | TIMOTHY BUXTON |