1377 N SERRANO AVE 90027

Certificate Information: 1377 N SERRANO AVE 90027

Application / Permit
19016-10000-38371
Plan Check / Job No.
B19LA25287
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
TENANT IMPROVEMENT OF (E) OFFICE FOR DIGITAL EDITING ON 1ST AND 2ND FLOOR.
Permit Issued
Issued on 3/6/2020
Issuing Office
Metro
Current Status
Permit Finaled on 5/17/2021

Permit Application Status History

Submitted 11/27/2019 APPLICANT
Assigned to Plan Check Engineer 12/5/2019 KEVIN MORALES
Corrections Issued 12/9/2019 KEVIN MORALES
Green Plans Picked Up 12/10/2019 APPLICANT
Quality Review Completed 12/15/2019 YOUNG KIM
Disabled Access Plans Picked Up 1/10/2020 APPLICANT
Plan Check Approved 2/3/2020 KEVIN MORALES
Issued 3/6/2020 LADBS
Building Plans Picked Up 4/2/2020 APPLICANT
Permit Finaled 5/17/2021 EDWIN GREGORYONA

Permit Application Clearance Information

"Q" conditions Cleared 1/3/2020 SARAH GOLDMAN
Comm Cor/Mini-Mall Cleared 1/3/2020 SARAH GOLDMAN
ZA Case Cleared 1/3/2020 SARAH GOLDMAN
ZA Case Cleared 1/3/2020 SARAH GOLDMAN
ZA Case Cleared 1/3/2020 SARAH GOLDMAN
ZA Case Cleared 1/3/2020 SARAH GOLDMAN
ZA Case Cleared 1/3/2020 SARAH GOLDMAN
Eng Process Fee Ord 176,300 Cleared 1/10/2020 JOHN LIN
Sewer availability Cleared 1/10/2020 JOHN LIN
Public Works-Highway Ded. Cleared 1/10/2020 JOHN LIN
Public Works-Open Permits Cleared 1/10/2020 JOHN LIN
Public Works-Sewers Cleared 1/10/2020 JOHN LIN
Green Code Cleared 1/24/2020 COLIN LOREDO
DAS Clearance Cleared 1/27/2020 KEVIN MORALES
Redevelopment Project Area Cleared 1/28/2020 GISELLE CORELLA
Comm Cor/Mini-Mall Cleared 1/29/2020 SARAH GOLDMAN

Contact Information

Architect Brennan,, Ross A; Lic. No.: C27858 7008 SANTA MONICA BLVD      HOLLYWOOD, CA 90038
Contractor K C S West Inc; Lic. No.: 908480-B 250 EAST 1ST STREET STE 600      LOS ANGELES, CA 90012
Engineer Mengelkoch,, Samuel Owen; Lic. No.: S5439 813 WILCOX AVE 203      LOS ANGELES, CA 90038

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Grading Pre-Inspection 5/27/2020 Not Ready for Inspection LANNY MERRICK
Excavation/Setback/Form/Re-Bar 6/2/2020 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 6/2/2020 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 6/11/2020 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 6/11/2020 Partial Inspection EDWIN GREGORYONA
Masonry Wall/Backfill 6/17/2020 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 6/18/2020 Partial Approval EDWIN GREGORYONA
Deputy Drilled-In Anchors 6/26/2020 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 6/29/2020 Partial Approval RUSSELL BONVOULOIR
Light Gage Steel Frame 6/29/2020 Partial Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 6/30/2020 Partial Approval EDWIN GREGORYONA
Deputy Drilled-In Anchors 7/7/2020 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 7/7/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 7/7/2020 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 7/7/2020 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 7/8/2020 Partial Approval EDWIN GREGORYONA
Drywall Nailing 7/10/2020 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 7/10/2020 Partial Approval EDWIN GREGORYONA
Structural Steel Frame 7/10/2020 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 7/17/2020 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 7/20/2020 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 7/20/2020 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 7/21/2020 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 7/27/2020 Partial Approval EDWIN GREGORYONA
Drywall Nailing 8/7/2020 Partial Approval RUSSELL BONVOULOIR
Drywall Nailing 8/17/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 8/25/2020 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 9/8/2020 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 9/11/2020 Partial Approval EDWIN GREGORYONA
Drywall Nailing 9/18/2020 Partial Inspection EDWIN GREGORYONA
Deputy Drilled-In Anchors 9/23/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 9/23/2020 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 9/25/2020 Partial Approval EDWIN GREGORYONA
Drywall Nailing 10/9/2020 Partial Inspection EDWIN GREGORYONA
Light Gage Steel Frame 10/9/2020 Partial Approval EDWIN GREGORYONA
Drywall Nailing 10/16/2020 Partial Approval EDWIN GREGORYONA
T-Bar Ceiling 10/20/2020 Partial Approval EDWIN GREGORYONA
Drywall Nailing 10/23/2020 Not Ready for Inspection EDWIN GREGORYONA
Drywall Nailing 10/26/2020 Partial Approval EDWIN GREGORYONA
T-Bar Ceiling 12/9/2020 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 12/18/2020 Partial Approval EDWIN GREGORYONA
Drywall Nailing 12/29/2020 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 1/20/2021 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 1/21/2021 Partial Inspection EDWIN GREGORYONA
Light Gage Steel Frame 2/2/2021 Approved EDWIN GREGORYONA
T-Bar Ceiling 2/12/2021 Approved EDWIN GREGORYONA
Smoke Detectors 2/25/2021 Approved EDWIN GREGORYONA
Final 3/25/2021 Partial Inspection EDWIN GREGORYONA
Green Building Final 3/25/2021 Approved EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 3/25/2021 SGSOV Approved EDWIN GREGORYONA
Final 5/12/2021 Partial Inspection EDWIN GREGORYONA
Final 5/17/2021 Permit Finaled EDWIN GREGORYONA