950 S GRAMERCY DR 90019
Certificate Information: 950 S GRAMERCY DR 90019
- Application / Permit
- 19016-10000-38363
- Plan Check / Job No.
- B19LA25273
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT-STORY RETROFIT AS PER LABC CH. 93. INSTALL (2) SCCS W/GB.
- Permit Issued
- Issued on 4/14/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 1/25/2021
Permit Application Status History
| Submitted | 11/27/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/11/2019 | JESSE VIDUYA |
| Corrections Issued | 12/16/2019 | JESSE VIDUYA |
| Quality Review Completed | 12/17/2019 | SAI KHUM |
| Building Plans Picked Up | 12/19/2019 | APPLICANT |
| Plan Check Approved | 1/15/2020 | JESSE VIDUYA |
| Issued | 4/14/2020 | LADBS |
| OK for CofC | 8/19/2020 | DARRYL ARNOLD |
| CofC Issued | 1/25/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 3/16/2020 | MICHAEL SOTO |
Contact Information
| Engineer | Funk,, David Lyle; Lic. No.: S5421 | 319 MAIN STREET EL SEGUNDO, CA 90245 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/27/2020 | Approved | DARRYL ARNOLD |
| Excavation/Setback/Form/Re-Bar | 7/29/2020 | Approved | DARRYL ARNOLD |
| Footing/Foundation/Slab | 7/29/2020 | Approved | DARRYL ARNOLD |
| Wood Frame | 7/29/2020 | Approved | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 7/30/2020 | Conditional Approval | MARK FERRARI |
| Interior/Exterior Lathing | 8/7/2020 | Approved | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 8/17/2020 | SGSOV Not Ready | DARRYL ARNOLD |
| Final | 8/19/2020 | OK for CofC | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 8/19/2020 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 8/19/2020 | Approved | DARRYL ARNOLD |