4420 N SIMPSON AVE 91607
Certificate Information: 4420 N SIMPSON AVE 91607
- Application / Permit
- 19016-10000-38359
- Plan Check / Job No.
- B19LA25269
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT-STORY RETROFIT AS PER LABC CH. 93. INSTALL SHEAR WALLS AND (1) STEEL CANTILEVER COLUMN
- Permit Issued
- Issued on 4/29/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 10/19/2020
Permit Application Status History
| Submitted | 11/27/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/11/2019 | HANS SANTIAGO |
| Corrections Issued | 12/16/2019 | HANS SANTIAGO |
| Quality Review Completed | 12/17/2019 | SAI KHUM |
| Building Plans Picked Up | 12/19/2019 | APPLICANT |
| Applicant returned to address corrections | 1/10/2020 | HANS SANTIAGO |
| Plan Check Approved | 1/30/2020 | ANDREW SANTIAGO |
| Plan Check Approved | 2/27/2020 | ANDREW SANTIAGO |
| Issued | 4/29/2020 | LADBS |
| OK for CofC | 10/19/2020 | MARK FERRARI |
| CofC Issued | 10/19/2020 | ERNESTO CORRAL |
Permit Application Clearance Information
| Encroachment in public way | Cleared | 2/6/2020 | ELAINE LEI |
| Eng Process Fee Ord 176,300 | Cleared | 2/20/2020 | ROSA SILVA |
| Work Adjacent to Public Way | Cleared | 2/20/2020 | ROSA SILVA |
| Tenant Habitability Plan | Cleared | 3/17/2020 | ISMAEL HERNANDEZ |
Contact Information
| Engineer | Funk,, David Lyle; Lic. No.: S5421 | 319 MAIN STREET EL SEGUNDO, CA 90245 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/14/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Reinf. Concrete | 5/28/2020 | No Access for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 5/28/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 5/28/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 5/28/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 5/29/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 5/29/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 5/29/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 6/1/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 6/1/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 6/1/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Reinf. Concrete | 6/2/2020 | Approved | JOE VELASQUEZ |
| Footing/Foundation/Slab | 6/2/2020 | Approved | JOE VELASQUEZ |
| Structural Steel Frame | 6/2/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 6/2/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2020 | Partial Approval | JOE VELASQUEZ |
| Wood Frame | 6/9/2020 | Partial Approval | JOE VELASQUEZ |
| Deputy Steel/Welding | 6/10/2020 | No Access for Inspection | JOE VELASQUEZ |
| Deputy Wood Construction | 6/10/2020 | No Access for Inspection | DANIEL VARNUM |
| Wood Frame | 6/10/2020 | Corrections Issued | DANIEL VARNUM |
| Deputy Wood Construction | 6/11/2020 | No Access for Inspection | JOE VELASQUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/11/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 6/11/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Interior/Exterior Lathing | 6/16/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Interior/Exterior Lathing | 6/17/2020 | Approved | JOE VELASQUEZ |
| Final | 7/8/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 7/8/2020 | SGSOV Not Ready | JOE VELASQUEZ |
| Smoke Detectors | 7/8/2020 | Approved | JOE VELASQUEZ |
| Final | 10/19/2020 | OK for CofC | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 10/19/2020 | SGSOV Approved | MARK FERRARI |