910 S SHERBOURNE DR 90035
Certificate Information: 910 S SHERBOURNE DR 90035
- Application / Permit
- 19016-10000-38358
- Plan Check / Job No.
- B19LA25265
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH 93. INSTALL NEW WOOD SHEAR WALL
- Permit Issued
- Issued on 9/16/2022
- Issuing Office
- Current Status
- CofC Issued on 9/5/2024
Permit Application Status History
| Submitted | 11/27/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/11/2019 | HANS SANTIAGO |
| Corrections Issued | 12/16/2019 | HANS SANTIAGO |
| Quality Review Completed | 12/17/2019 | SAI KHUM |
| Building Plans Picked Up | 12/19/2019 | APPLICANT |
| Applicant returned to address corrections | 12/24/2019 | HANS SANTIAGO |
| Plan Check Approved | 4/1/2020 | ANDREW SANTIAGO |
| Issued | 9/16/2022 | APPLICANT |
| OK for CofC | 8/29/2023 | DARRYL ARNOLD |
| OK for CofC | 8/29/2023 | DARRYL ARNOLD |
| CofC Issued | 9/5/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 9/15/2022 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Alpha Structural Inc; Lic. No.: 663409-B | 8334 FOOTHILL BLVD SUNLAND, CA 91040 |
| Engineer | Demers,, Joe Alan; Lic. No.: C71535 | 1626 S MAYFLOWER AVE UNIT B MONROVIA, CA 91016 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wall Anchors | 11/3/2022 | Approved | DARRYL ARNOLD |
| Wood Frame | 11/3/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Wood Construction | 11/7/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Steel/Welding | 11/8/2022 | Conditional Approval | DARRYL ARNOLD |
| Structural Steel Frame | 11/10/2022 | Approved | DARRYL ARNOLD |
| Interior/Exterior Lathing | 11/18/2022 | Conditional Approval | DARRYL ARNOLD |
| Final | 12/5/2022 | Not Ready for Inspection | DARRYL ARNOLD |
| METHANE-Final | 12/5/2022 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 12/5/2022 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 12/5/2022 | Corrections Issued | DARRYL ARNOLD |
| Final | 12/8/2022 | Not Ready for Inspection | DARRYL ARNOLD |
| METHANE-Final | 12/8/2022 | Approved | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 12/8/2022 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 12/8/2022 | Not Ready for Inspection | DARRYL ARNOLD |
| Final | 8/24/2023 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 8/24/2023 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 8/24/2023 | Conditional Approval | DARRYL ARNOLD |
| Final | 8/29/2023 | OK for CofC | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 8/29/2023 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 8/29/2023 | Approved | DARRYL ARNOLD |