5333 W JEFFERSON BLVD 90016
Certificate Information: 5333 W JEFFERSON BLVD 90016
- Application / Permit
- 19016-10000-38328
- Plan Check / Job No.
- B19LA25253
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- INSTALLATION OF HIGH PILE RACK IN (E) WAREHOUSE
- Permit Issued
- Issued on 2/10/2020
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 4/3/2020
Permit Application Status History
| Submitted | 11/27/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/24/2019 | EMMANUEL MARTINEZ |
| Corrections Issued | 12/31/2019 | EMMANUEL MARTINEZ |
| Green Plans Picked Up | 1/14/2020 | APPLICANT |
| Quality Review Completed | 1/16/2020 | ARMEN JIVALAGIAN |
| Building Plans Picked Up | 1/23/2020 | APPLICANT |
| Plan Check Approved | 2/10/2020 | EMMANUEL MARTINEZ |
| Issued | 2/10/2020 | LADBS |
| Permit Finaled | 4/3/2020 | TIMOTHY BUXTON |
Permit Application Clearance Information
| Community Plan Implem. Overlay | Cleared | 1/31/2020 | JASON CHAN |
| DAS Clearance | Cleared | 1/31/2020 | EMMANUEL MARTINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/31/2020 | ERIK BEASLEY |
| Green Code | Cleared | 1/31/2020 | VIVIAN LAO |
| Miscellaneous | Cleared | 1/31/2020 | TERRY PHAN |
| ZI | Cleared | 1/31/2020 | JASON CHAN |
| High storage rack | Cleared | 2/7/2020 | WILLIAM JOHNS |
Contact Information
| Architect | Acciarri,, Robert; Lic. No.: C32106 | 32291 ACACIA CT AVON LAKE, OH 440122502 |
| Contractor | Empire Racks; Lic. No.: 1026768-D24 | 4806 FAUNA ST MONTCLAIR, CA 91763 |
| Engineer | Tlumak,, Jordan Michael; Lic. No.: C85278 | PO BOX BRENTWOOD, TN 37024 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/11/2020 | Conditional Approval | TIMOTHY BUXTON |
| Final | 2/11/2020 | Partial Inspection | TIMOTHY BUXTON |
| Green Building Final | 2/11/2020 | Not Ready for Inspection | TIMOTHY BUXTON |
| SGSOV-Seismic Gas S/O Valve | 2/11/2020 | SGSOV Not Ready | TIMOTHY BUXTON |
| Smoke Detectors | 2/11/2020 | Approved | TIMOTHY BUXTON |
| Deputy Drilled-In Anchors | 3/19/2020 | Conditional Approval | TIMOTHY BUXTON |
| Final | 3/25/2020 | Not Ready for Inspection | TIMOTHY BUXTON |
| Green Building Final | 3/25/2020 | Approved | TIMOTHY BUXTON |
| SGSOV-Seismic Gas S/O Valve | 3/25/2020 | SGSOV No Gas | TIMOTHY BUXTON |
| Final | 4/3/2020 | Permit Finaled | TIMOTHY BUXTON |