2318 1/2 S LUCERNE AVE 90016

Certificate Information: 2318 1/2 S LUCERNE AVE 90016

Application / Permit
19016-10000-38290
Plan Check / Job No.
B19LA25222
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED CONVERSION OF GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229
Permit Issued
Issued on 8/6/2020
Issuing Office
Current Status
CofO Issued on 7/3/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/27/2019 APPLICANT
Assigned to Plan Check Engineer 11/27/2019 SINA KHOSRAVI
Corrections Issued 11/27/2019 SINA KHOSRAVI
Plan Check Approved 3/6/2020 MIGUEL JIMENEZ
Issued 8/6/2020 APPLICANT
CofO in Progress 6/17/2021 STUART CHAPMAN
Permit Finaled 7/3/2021 DEROLD HAUFF
CofO Issued 7/3/2021 DEROLD HAUFF
Permit Finaled 7/3/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/27/2019 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 11/27/2019 JEANIE LAM
Sewer availability Cleared 11/27/2019 JEANIE LAM
Construction near power lines Cleared 1/22/2020 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Kim,, Hong Kook; Lic. No.: C64529 839 S MUIRFIELD RD      LOS ANGELES, CA 90005

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/21/2020 Approved STUART CHAPMAN
Footing/Foundation/Slab 8/21/2020 Approved STUART CHAPMAN
BUILDING-Rough-Frame 10/9/2020 Partial Approval STUART CHAPMAN
ELECTRICAL-Rough 10/9/2020 Approved STUART CHAPMAN
Green Building Rough 10/9/2020 Approved STUART CHAPMAN
MERV13>=Rough 10/9/2020 Approved STUART CHAPMAN
ELECTRICAL-Rough 11/19/2020 Approved STUART CHAPMAN
Green Building Rough 11/19/2020 Approved STUART CHAPMAN
HVAC-Rough 11/19/2020 Approved STUART CHAPMAN
Interior/Exterior Lathing 11/19/2020 Partial Approval STUART CHAPMAN
PLUMBING-Rough 11/19/2020 Approved STUART CHAPMAN
Insulation 11/25/2020 Approved STUART CHAPMAN
BUILDING-Rough-Frame 12/2/2020 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 12/2/2020 Approved STUART CHAPMAN
Drywall Nailing 12/4/2020 Approved STUART CHAPMAN
Shower Pan 12/17/2020 Approved STUART CHAPMAN
Service/Power Release 1/11/2021 Not Ready for Inspection STUART CHAPMAN
ELECTRICAL-Final 5/6/2021 Not Ready for Inspection STUART CHAPMAN
Final 5/6/2021 Corrections Issued STUART CHAPMAN
Green Building Final 5/6/2021 Approved STUART CHAPMAN
MERV13>=Final 5/6/2021 Approved STUART CHAPMAN
PLUMBING-Final 5/6/2021 Not Ready for Inspection STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 5/6/2021 SGSOV Not Required STUART CHAPMAN
Smoke Detectors 5/6/2021 Approved STUART CHAPMAN
Final 5/24/2021 Not Ready for Inspection STUART CHAPMAN
ELECTRICAL-Final 6/3/2021 Approved STUART CHAPMAN
Final 6/3/2021 Partial Approval STUART CHAPMAN
HVAC-Final 6/3/2021 Approved STUART CHAPMAN
PLUMBING-Final 6/3/2021 Approved STUART CHAPMAN