3848 S WELLINGTON ROAD 90008

Certificate Information: 3848 S WELLINGTON ROAD 90008

Application / Permit
19016-10000-38170
Plan Check / Job No.
B19LA25135
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (E) 18'x20' garage into accessory dwelling unit per AB 494 and SB 229. No change in building footprint.
Permit Issued
Issued on 2/4/2020
Issuing Office
Metro
Current Status
Issued on 2/4/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/26/2019 APPLICANT
Assigned to Plan Check Engineer 12/13/2019 MONICA RAMIREZ
Corrections Issued 12/13/2019 MONICA RAMIREZ
Plan Check Approved 2/4/2020 TU HUA
Issued 2/4/2020 LADBS

Permit Application Clearance Information

Address approval Cleared 2/4/2020 ELAINE LEI
Construction within easement Cleared 2/4/2020 TORI CHEN
Eng Process Fee Ord 176,300 Cleared 2/4/2020 ELAINE LEI
Sewer availability Cleared 2/4/2020 ELAINE LEI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/27/2020 Partial Approval COREY HUPP
Gas Test 3/3/2020 Not Ready for Inspection COREY HUPP
PLUMBING-Rough 3/3/2020 Not Ready for Inspection COREY HUPP
PLUMBING-Rough 3/6/2020 Not Ready for Inspection COREY HUPP
Footing/Foundation/Slab 3/10/2020 Approved COREY HUPP
BUILDING-Rough-Frame 3/16/2020 Not Ready for Inspection COREY HUPP
Green Building Rough 3/16/2020 Not Ready for Inspection COREY HUPP
ELECTRICAL-Rough 3/24/2020 Not Ready for Inspection COREY HUPP
PLUMBING-Rough 3/24/2020 Approved COREY HUPP
BUILDING-Rough-Frame 3/26/2020 Approved COREY HUPP
Green Building Rough 3/26/2020 Approved COREY HUPP
ELECTRICAL-Rough 4/30/2020 Not Ready for Inspection COREY HUPP
ELECTRICAL-Rough 5/1/2020 Approved COREY HUPP
Insulation 5/5/2020 Approved COREY HUPP
Floor/Roof Diaphrgm/Shear Wall 5/11/2020 Not Ready for Inspection ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 5/12/2020 Not Ready for Inspection FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 5/19/2020 Approved ROBERT MCDOWELL
Drywall Nailing 5/29/2020 Not Ready for Inspection SABAS ALONSO
Special/Order Compliance 5/29/2020 Corrections Issued SABAS ALONSO
Drywall Nailing 6/2/2020 Approved SABAS ALONSO
Shower Pan 6/4/2020 Not Ready for Inspection SABAS ALONSO
Interior/Exterior Lathing 6/11/2020 Not Ready for Inspection SABAS ALONSO
Shower Pan 6/12/2020 Partial Approval SABAS ALONSO
Interior/Exterior Lathing 6/16/2020 Partial Approval SABAS ALONSO
Shower Pan 6/16/2020 Not Ready for Inspection SABAS ALONSO
Shower Pan 6/18/2020 Approved SABAS ALONSO
Special/Order Compliance 6/22/2020 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 2/5/2021 SGSOV Not Ready FREDDIE RIVERA
Final 2/25/2021 Corrections Issued DAVID FEILER
Green Building Final 2/25/2021 Not Ready for Inspection DAVID FEILER
SGSOV-Seismic Gas S/O Valve 2/25/2021 SGSOV Not Ready DAVID FEILER
Smoke Detectors 2/25/2021 Approved DAVID FEILER
Final 3/31/2021 Not Ready for Inspection DAVID FEILER
Green Building Final 3/31/2021 Not Ready for Inspection DAVID FEILER
SGSOV-Seismic Gas S/O Valve 3/31/2021 SGSOV Approved DAVID FEILER