3848 S WELLINGTON ROAD 90008
Certificate Information: 3848 S WELLINGTON ROAD 90008
- Application / Permit
- 19016-10000-38170
- Plan Check / Job No.
- B19LA25135
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) 18'x20' garage into accessory dwelling unit per AB 494 and SB 229. No change in building footprint.
- Permit Issued
- Issued on 2/4/2020
- Issuing Office
- Metro
- Current Status
- Issued on 2/4/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/26/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/13/2019 | MONICA RAMIREZ |
| Corrections Issued | 12/13/2019 | MONICA RAMIREZ |
| Plan Check Approved | 2/4/2020 | TU HUA |
| Issued | 2/4/2020 | LADBS |
Permit Application Clearance Information
| Address approval | Cleared | 2/4/2020 | ELAINE LEI |
| Construction within easement | Cleared | 2/4/2020 | TORI CHEN |
| Eng Process Fee Ord 176,300 | Cleared | 2/4/2020 | ELAINE LEI |
| Sewer availability | Cleared | 2/4/2020 | ELAINE LEI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/27/2020 | Partial Approval | COREY HUPP |
| Gas Test | 3/3/2020 | Not Ready for Inspection | COREY HUPP |
| PLUMBING-Rough | 3/3/2020 | Not Ready for Inspection | COREY HUPP |
| PLUMBING-Rough | 3/6/2020 | Not Ready for Inspection | COREY HUPP |
| Footing/Foundation/Slab | 3/10/2020 | Approved | COREY HUPP |
| BUILDING-Rough-Frame | 3/16/2020 | Not Ready for Inspection | COREY HUPP |
| Green Building Rough | 3/16/2020 | Not Ready for Inspection | COREY HUPP |
| ELECTRICAL-Rough | 3/24/2020 | Not Ready for Inspection | COREY HUPP |
| PLUMBING-Rough | 3/24/2020 | Approved | COREY HUPP |
| BUILDING-Rough-Frame | 3/26/2020 | Approved | COREY HUPP |
| Green Building Rough | 3/26/2020 | Approved | COREY HUPP |
| ELECTRICAL-Rough | 4/30/2020 | Not Ready for Inspection | COREY HUPP |
| ELECTRICAL-Rough | 5/1/2020 | Approved | COREY HUPP |
| Insulation | 5/5/2020 | Approved | COREY HUPP |
| Floor/Roof Diaphrgm/Shear Wall | 5/11/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2020 | Approved | ROBERT MCDOWELL |
| Drywall Nailing | 5/29/2020 | Not Ready for Inspection | SABAS ALONSO |
| Special/Order Compliance | 5/29/2020 | Corrections Issued | SABAS ALONSO |
| Drywall Nailing | 6/2/2020 | Approved | SABAS ALONSO |
| Shower Pan | 6/4/2020 | Not Ready for Inspection | SABAS ALONSO |
| Interior/Exterior Lathing | 6/11/2020 | Not Ready for Inspection | SABAS ALONSO |
| Shower Pan | 6/12/2020 | Partial Approval | SABAS ALONSO |
| Interior/Exterior Lathing | 6/16/2020 | Partial Approval | SABAS ALONSO |
| Shower Pan | 6/16/2020 | Not Ready for Inspection | SABAS ALONSO |
| Shower Pan | 6/18/2020 | Approved | SABAS ALONSO |
| Special/Order Compliance | 6/22/2020 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 2/5/2021 | SGSOV Not Ready | FREDDIE RIVERA |
| Final | 2/25/2021 | Corrections Issued | DAVID FEILER |
| Green Building Final | 2/25/2021 | Not Ready for Inspection | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 2/25/2021 | SGSOV Not Ready | DAVID FEILER |
| Smoke Detectors | 2/25/2021 | Approved | DAVID FEILER |
| Final | 3/31/2021 | Not Ready for Inspection | DAVID FEILER |
| Green Building Final | 3/31/2021 | Not Ready for Inspection | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 3/31/2021 | SGSOV Approved | DAVID FEILER |