5121 N LEDGE AVE 91601
Certificate Information: 5121 N LEDGE AVE 91601
- Application / Permit
- 19016-10000-38003
- Plan Check / Job No.
- B19LA25057
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (35) Condo-Multi Family
- Work Description
- SOFT-STORY RETROFIT AS PER LABC CH. 93. INSTALL (1) SCCS.
- Permit Issued
- Issued on 9/16/2020
- Issuing Office
- Current Status
- CofC Issued on 3/17/2021
Permit Application Status History
| Submitted | 11/25/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/18/2019 | JESSE VIDUYA |
| Corrections Issued | 12/23/2019 | JESSE VIDUYA |
| Quality Review Completed | 12/27/2019 | SAI KHUM |
| Building Plans Picked Up | 1/8/2020 | APPLICANT |
| Plan Check Approved | 1/23/2020 | JESSE VIDUYA |
| Issued | 9/16/2020 | APPLICANT |
| OK for CofC | 2/17/2021 | KENNETH ROBERTS |
| CofC Issued | 3/17/2021 | RICKEY JACKSON |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 8/31/2020 | STEVEN HOFSTAD |
Contact Information
| Contractor | Optimum Seismic Inc; Lic. No.: 1012702-B | 5508 S SANTA FE AVENUE VERNON, CA 90058 |
| Engineer | Mirmohammadsadeghi,, Kamaleddin; Lic. No.: C53468 | 1377 S BEVERLY GLEN BLVD 308 LOS ANGELES, CA 90024 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/25/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Steel/Welding | 10/13/2020 | Conditional Approval | JONATHAN QUACH |
| Footing/Foundation/Slab | 10/16/2020 | Corrections Issued | JOE VELASQUEZ |
| Structural Steel Frame | 10/16/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 10/16/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 10/21/2020 | Approved | JOE VELASQUEZ |
| Structural Steel Frame | 10/21/2020 | Approved | JOE VELASQUEZ |
| Wood Frame | 10/21/2020 | Approved | JOE VELASQUEZ |
| Interior/Exterior Lathing | 11/5/2020 | Approved | JOE VELASQUEZ |
| Final | 2/3/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 2/3/2021 | SGSOV Not Ready | JOE VELASQUEZ |
| Smoke Detectors | 2/3/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Final | 2/16/2021 | Partial Approval | HAMID PISHEHVAR |
| SGSOV-Seismic Gas S/O Valve | 2/16/2021 | SGSOV Approved | HAMID PISHEHVAR |
| Smoke Detectors | 2/16/2021 | Approved | HAMID PISHEHVAR |
| Final | 2/17/2021 | OK for CofC | KENNETH ROBERTS |