1103 S ABBOT KINNEY BLVD 90291
Certificate Information: 1103 S ABBOT KINNEY BLVD 90291
- Application / Permit
- 19016-10000-37993
- Plan Check / Job No.
- B19LA25055
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- INTERIOR TI OF (E) RETAIL STORE & ROOFTOP PLATFORM FOR MECH. EQUIPMENT.
- Permit Issued
- Issued on 1/23/2020
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 6/10/2020
Permit Application Status History
| Submitted | 11/25/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/3/2019 | KEVIN MORALES |
| Corrections Issued | 12/4/2019 | KEVIN MORALES |
| Plan Check Approved | 1/16/2020 | KEVIN MORALES |
| Issued | 1/23/2020 | LADBS |
| Permit Finaled | 6/9/2020 | SORIN CIRSTOIU |
Permit Application Clearance Information
| Specific Plan | Cleared | 1/6/2020 | BINDU KANNAN |
Contact Information
| Contractor | Weinbaum Construction; Lic. No.: 1048505-B | 1465 ELIN POINTE DR EL SEGUNDO, CA 90245 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 2/11/2020 | Partial Approval | JASON BORUTA |
| Light Gage Steel Frame | 2/11/2020 | Partial Approval | JASON BORUTA |
| Pre-Inspection | 2/11/2020 | Corrections Issued | JASON BORUTA |
| Excavation/Setback/Form/Re-Bar | 2/12/2020 | Not Ready for Inspection | JASON BORUTA |
| Drywall Nailing | 2/27/2020 | Partial Approval | SORIN CIRSTOIU |
| Insulation | 2/27/2020 | Partial Approval | SORIN CIRSTOIU |
| Light Gage Steel Frame | 4/3/2020 | Partial Approval | SORIN CIRSTOIU |
| Final | 5/27/2020 | Partial Inspection | SORIN CIRSTOIU |
| Green Building Final | 5/27/2020 | Partial Inspection | SORIN CIRSTOIU |
| SGSOV-Seismic Gas S/O Valve | 5/27/2020 | SGSOV Not Ready | SORIN CIRSTOIU |
| Smoke Detectors | 5/27/2020 | Partial Inspection | SORIN CIRSTOIU |
| SGSOV-Seismic Gas S/O Valve | 6/2/2020 | SGSOV Not Ready | SORIN CIRSTOIU |
| Pre-Inspection | 6/4/2020 | Approved | SORIN CIRSTOIU |
| Final | 6/9/2020 | Permit Finaled | SORIN CIRSTOIU |
| Green Building Final | 6/9/2020 | Approved | SORIN CIRSTOIU |
| SGSOV-Seismic Gas S/O Valve | 6/9/2020 | SGSOV Approved | SORIN CIRSTOIU |