4427 W FINLEY AVE 90027
Certificate Information: 4427 W FINLEY AVE 90027
- Application / Permit
- 19016-10000-37939
- Plan Check / Job No.
- B19LA25002
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93: Install (1) STEEL SPECIAL CANTILEVER COLUMN
- Permit Issued
- Issued on 8/22/2022
- Issuing Office
- Current Status
- CofC Issued on 12/20/2022
Permit Application Status History
| Submitted | 11/22/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/18/2019 | DANIEL SANJUAN |
| Corrections Issued | 12/30/2019 | THOMAS SHERMAN |
| Quality Review Completed | 1/6/2020 | HANS SANTIAGO |
| Applicant returned to address corrections | 2/18/2021 | DANIEL SANJUAN |
| Plan Check Approved | 5/5/2022 | DANIEL SANJUAN |
| Issued | 8/22/2022 | APPLICANT |
| OK for CofC | 12/19/2022 | VAHE KELEDJIAN |
| CofC Issued | 12/20/2022 | WINSTON DUNNING |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 8/17/2022 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Titan Contracting Services Inc; Lic. No.: 976552-B | 13434 RAYMER STREET NORTH HOLLYWOOD, CA 91605 |
| Engineer | Lara,, Arath Saude; Lic. No.: C68626 | 7778 VALLE VISTA DRIVE RANCHO CUCAMONGA, CA 91730 |
| Engineer | Lara,, Arath Saude; Lic. No.: NA68626 | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/18/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 11/18/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Steel/Welding | 11/18/2022 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 11/22/2022 | Corrections Issued | VAHE KELEDJIAN |
| Structural Steel Frame | 11/22/2022 | Corrections Issued | VAHE KELEDJIAN |
| Wood Frame | 11/22/2022 | Corrections Issued | VAHE KELEDJIAN |
| Footing/Foundation/Slab | 12/2/2022 | Conditional Approval | VAHE KELEDJIAN |
| Wood Frame | 12/2/2022 | Conditional Approval | VAHE KELEDJIAN |
| Interior/Exterior Lathing | 12/8/2022 | Approved | VAHE KELEDJIAN |
| Final | 12/19/2022 | OK for CofC | VAHE KELEDJIAN |
| SGSOV-Seismic Gas S/O Valve | 12/19/2022 | SGSOV Approved | VAHE KELEDJIAN |
| Smoke Detectors | 12/19/2022 | Approved | VAHE KELEDJIAN |