10548 W EASTBORNE AVE 90024
Certificate Information: 10548 W EASTBORNE AVE 90024
- Application / Permit
- 19016-10000-37891
- Plan Check / Job No.
- B19LA24970
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- E plan - Soft-Story seismic retrofit per LABC Chapter 93: INSTALL STEEL CANTILEVER COLUMNS.
- Permit Issued
- Issued on 7/27/2021
- Issuing Office
- Current Status
- CofC Issued on 12/8/2021
Permit Application Status History
| Submitted | 12/23/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/15/2020 | DANIEL YIP |
| Corrections Issued | 1/22/2020 | DANIEL YIP |
| Quality Review Completed | 1/27/2020 | HANS SANTIAGO |
| Applicant returned to address corrections | 4/29/2020 | DANIEL YIP |
| Plan Check Approved | 5/15/2020 | DANIEL YIP |
| Issued | 7/27/2021 | APPLICANT |
| OK for CofC | 12/7/2021 | GRANT WOODS |
| CofC Issued | 12/8/2021 | DAVID TSAU |
Permit Application Clearance Information
| Specific Plan | Cleared | 4/15/2020 | KENTON TRINH |
| Tenant Habitability Plan | Cleared | 6/15/2021 | MICHAEL SOTO |
Contact Information
| Contractor | Cha Kyungmin; Lic. No.: 1018067-B | 917 S NEW HAMPSHIRE AVENUE 103 LOS ANGELES, CA 90006 |
| Engineer | Shekaramiz,, Hamid; Lic. No.: C82784 | 2 TIMBRE RANCHO SANTA MARGARITA, CA 92688 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/23/2021 | Approved | SORIN CIRSTOIU |
| Footing/Foundation/Slab | 9/21/2021 | Partial Approval | SORIN CIRSTOIU |
| Deputy Reinf. Concrete | 9/23/2021 | Conditional Approval | GRANT WOODS |
| Deputy Steel/Welding | 10/19/2021 | Conditional Approval | GRANT WOODS |
| Footing/Foundation/Slab | 11/3/2021 | Approved | GRANT WOODS |
| Structural Steel Frame | 11/3/2021 | Approved | GRANT WOODS |
| Wood Frame | 11/3/2021 | Approved | GRANT WOODS |
| Drywall Nailing | 11/15/2021 | Approved | PAUL DAVIDSON |
| Interior/Exterior Lathing | 11/15/2021 | Not Ready for Inspection | PAUL DAVIDSON |
| Interior/Exterior Lathing | 11/19/2021 | Approved | GRANT WOODS |
| Final | 12/7/2021 | OK for CofC | GRANT WOODS |
| METHANE-Final | 12/7/2021 | Approved | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 12/7/2021 | SGSOV Approved | GRANT WOODS |
| Smoke Detectors | 12/7/2021 | Approved | GRANT WOODS |