745 N ORANGE DR 90038
Certificate Information: 745 N ORANGE DR 90038
- Application / Permit
- 19016-10000-37861
- Plan Check / Job No.
- B19LA24948
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF (E) 2-CAR GARAGE WITH ATTACHED 2 STORY HOBBY ROOM TO (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229 W/INCIDENTAL STORAGE ON 1ST FLOOR "COMPLY WITH DEPARTMENT ORDER effective date 08/01/2018. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 5/11/2020
- Issuing Office
- Current Status
- CofO Issued on 5/4/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/22/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/5/2019 | LAMAR DAVIS |
| Green Plans Picked Up | 12/10/2019 | APPLICANT |
| Corrections Issued | 12/11/2019 | LAMAR DAVIS |
| Quality Review Completed | 12/19/2019 | BILL STUTSMAN |
| Building Plans Picked Up | 1/16/2020 | APPLICANT |
| Plan Check Approved | 4/3/2020 | LAMAR DAVIS |
| Issued | 5/11/2020 | APPLICANT |
| CofO in Progress | 9/30/2020 | ARIS ALLAHVERDIAN |
| CofO in Progress | 9/30/2020 | ARIS ALLAHVERDIAN |
| Permit Finaled | 5/4/2022 | DANIEL SANCHEZ |
| CofO Issued | 5/4/2022 | DANIEL SANCHEZ |
| Permit Finaled | 5/4/2022 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Hold | Cleared | 1/10/2020 | CYNTHIA RYAN |
| Construction near power lines | Cleared | 1/22/2020 | RIDWAN HARDY |
| Address approval | Cleared | 3/2/2020 | THAN WIN |
| Sewer availability | Cleared | 3/2/2020 | THAN WIN |
| Eng Process Fee Ord 176,300 | Cleared | 3/5/2020 | PAMELA TENEZA |
| Green Code | Cleared | 3/24/2020 | COLIN LOREDO |
Contact Information
| Contractor | Design & Build Partners Inc; Lic. No.: 1053740-B | 13340 SATICOY ST #K NORTH HOLLYWOOD, CA 91605 |
Inspector Information
| PETER RUBIO, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN TCHANG, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| RYAN TAGUINES, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 5/14/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 5/15/2020 | Not Ready for Inspection | PATRICK QUALEY |
| ELECTRICAL-Rough | 5/15/2020 | Not Ready for Inspection | PATRICK QUALEY |
| Green Building Rough | 5/15/2020 | Not Ready for Inspection | PATRICK QUALEY |
| METHANE-Rough | 5/15/2020 | Not Ready for Inspection | PATRICK QUALEY |
| ELECTRICAL-Rough | 5/26/2020 | Partial Approval | ARIS ALLAHVERDIAN |
| PLUMBING-Rough | 5/26/2020 | Corrections Issued | ARIS ALLAHVERDIAN |
| PLUMBING-Rough | 5/29/2020 | Conditional Approval | PATRICK QUALEY |
| PLUMBING-Rough | 6/2/2020 | Not Ready for Inspection | ARIS ALLAHVERDIAN |
| Shower Pan | 6/4/2020 | Not Ready for Inspection | ARIS ALLAHVERDIAN |
| Shower Pan | 6/5/2020 | Approved | ARIS ALLAHVERDIAN |
| Interior/Exterior Lathing | 6/9/2020 | Approved | ARIS ALLAHVERDIAN |
| ELECTRICAL-Rough | 6/24/2020 | Approved | ARIS ALLAHVERDIAN |
| PLUMBING-Rough | 6/24/2020 | Approved | ARIS ALLAHVERDIAN |
| BUILDING-Rough-Frame | 6/30/2020 | Approved | ARIS ALLAHVERDIAN |
| Final | 6/30/2020 | Partial Approval | ARIS ALLAHVERDIAN |
| Green Building Final | 6/30/2020 | Approved | ARIS ALLAHVERDIAN |
| Green Building Rough | 6/30/2020 | Approved | ARIS ALLAHVERDIAN |
| METHANE-Final | 6/30/2020 | Approved | ARIS ALLAHVERDIAN |
| METHANE-Rough | 6/30/2020 | Approved | ARIS ALLAHVERDIAN |
| SGSOV-Seismic Gas S/O Valve | 6/30/2020 | SGSOV Approved | ARIS ALLAHVERDIAN |
| Smoke Detectors | 6/30/2020 | Approved | ARIS ALLAHVERDIAN |
| Final | 9/30/2020 | OK to Issue CofO | ARIS ALLAHVERDIAN |