901 N MARIPOSA AVE 90029

Certificate Information: 901 N MARIPOSA AVE 90029

Application / Permit
19016-10000-37820
Plan Check / Job No.
B19LA24904
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT AS PER LABC CH 93. INSTALL 12 SPECIAL CANTILEVER COLUMN AND WOOD FRAME SHEAR WALL.
Permit Issued
Issued on 5/15/2020
Issuing Office
Metro
Current Status
CofC Issued on 3/5/2021

Permit Application Status History

Submitted 11/22/2019 APPLICANT
Assigned to Plan Check Engineer 12/4/2019 JESSE VIDUYA
Corrections Issued 12/10/2019 JESSE VIDUYA
Quality Review Completed 12/11/2019 SAI KHUM
Building Plans Picked Up 12/12/2019 APPLICANT
Plan Check Approved 2/4/2020 JESSE VIDUYA
Issued 5/15/2020 LADBS
OK for CofC 3/4/2021 JONATHAN QUACH
CofC Issued 3/5/2021 ERNESTO CORRAL

Permit Application Clearance Information

Tenant Habitability Plan Cleared 4/30/2020 MICHAEL GREGERSON

Contact Information

Contractor K3m Building Contractors Inc; Lic. No.: 1046266-B 3660 WILSHIRE BLVD SUITE 818      LOS ANGELES, CA 90010
Engineer Abdelhafeez,, Haitham Abbas; Lic. No.: C63359 1451 S HACIENDA ST      ANAHEIM, CA 92804

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/17/2020 Approved MARK FERRARI
Wood Frame 11/4/2020 Partial Approval JONATHAN QUACH
Excavation/Setback/Form/Re-Bar 12/7/2020 Approved MARK FERRARI
Wall Anchors 12/10/2020 No Access for Inspection JONATHAN QUACH
Wood Frame 12/10/2020 No Access for Inspection JONATHAN QUACH
Wall Anchors 12/11/2020 Partial Approval JONATHAN QUACH
Wood Frame 12/11/2020 Partial Inspection JONATHAN QUACH
Wall Anchors 12/17/2020 Not Ready for Inspection JONATHAN QUACH
Wood Frame 12/17/2020 Not Ready for Inspection JONATHAN QUACH
Deputy Steel/Welding 12/21/2020 Conditional Approval JONATHAN QUACH
Wall Anchors 12/31/2020 Partial Approval JONATHAN QUACH
Wood Frame 12/31/2020 Partial Approval JONATHAN QUACH
Deputy Steel/Welding 1/8/2021 Conditional Approval FRED WOHLFARTH
Interior/Exterior Lathing 1/27/2021 Corrections Issued MARK FERRARI
Final 3/4/2021 OK for CofC JONATHAN QUACH
SGSOV-Seismic Gas S/O Valve 3/4/2021 SGSOV Approved JONATHAN QUACH
Smoke Detectors 3/4/2021 Approved JONATHAN QUACH