21901 W LASSEN ST BLDG 2 91311
Certificate Information: 21901 W LASSEN ST BLDG 2 91311
- Application / Permit
- 19016-10000-37805
- Plan Check / Job No.
- B19LA24900
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (35) Condo-Single Family
- Work Description
- SOFT STORY RETROFIT PER LABC CHAPTER 93. INSTALL STEEL CANTILEVER COLUMNS.
- Permit Issued
- Issued on 9/15/2021
- Issuing Office
- Current Status
- CofC Issued on 6/21/2022
Permit Application Status History
| Submitted | 11/22/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/4/2019 | MANUEL MONTUFAR |
| Corrections Issued | 12/10/2019 | MANUEL MONTUFAR |
| Quality Review Completed | 12/12/2019 | HANS SANTIAGO |
| Building Plans Picked Up | 12/30/2019 | APPLICANT |
| Plan Check Approved | 2/19/2020 | MANUEL MONTUFAR |
| Issued | 9/15/2021 | APPLICANT |
| OK for CofC | 5/18/2022 | KENNETH ROBERTS |
| CofC Issued | 6/21/2022 | KENNETH ROBERTS |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 8/9/2021 | PHILLIP MUNGUIA |
Contact Information
| Contractor | One Stop Retrofit; Lic. No.: 1026051-B | 18455 BURBANK BLVD STE 411 TARZANA, CA 91356 |
| Engineer | Namdar,, Mansour Tom; Lic. No.: S2976 | 16867 SEVERO PLACE ENCINO, CA 91436 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/8/2021 | Partial Inspection | DANIEL VARNUM |
| Deputy Steel/Welding | 10/18/2021 | Conditional Approval | KENNETH ROBERTS |
| Footing/Foundation/Slab | 10/22/2021 | Approved | KENNETH ROBERTS |
| Structural Steel Frame | 10/22/2021 | Approved | KENNETH ROBERTS |
| Deputy Wood Construction | 11/9/2021 | Conditional Approval | KENNETH ROBERTS |
| Deputy Wood Construction | 11/10/2021 | Conditional Approval | KENNETH ROBERTS |
| Deputy Wood Construction | 11/12/2021 | Conditional Approval | KENNETH ROBERTS |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2021 | Approved | KENNETH ROBERTS |
| Wood Frame | 12/2/2021 | Approved | KENNETH ROBERTS |
| Wood Frame | 12/7/2021 | Approved | KENNETH ROBERTS |
| Drywall Nailing | 12/13/2021 | Not Ready for Inspection | KENNETH ROBERTS |
| Drywall Nailing | 1/5/2022 | Approved | DANIEL VARNUM |
| Final | 1/19/2022 | Corrections Issued | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 1/19/2022 | SGSOV Gas Company | KENNETH ROBERTS |
| Smoke Detectors | 1/19/2022 | Not Ready for Inspection | KENNETH ROBERTS |
| Final | 5/18/2022 | OK for CofC | KENNETH ROBERTS |
| Smoke Detectors | 5/18/2022 | Approved | KENNETH ROBERTS |