1707 S BROCKTON AVE 90025
Certificate Information: 1707 S BROCKTON AVE 90025
- Application / Permit
- 19016-10000-37802
- Plan Check / Job No.
- B19LA24901
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH 93. INSTALL STRONG WALL AND 1 MOMENT FRAME.
- Permit Issued
- Issued on 2/27/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 12/31/2024
Permit Application Status History
| Submitted | 11/22/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/4/2019 | JESSE VIDUYA |
| Corrections Issued | 12/10/2019 | JESSE VIDUYA |
| Quality Review Completed | 12/11/2019 | SAI KHUM |
| Building Plans Picked Up | 12/12/2019 | APPLICANT |
| Plan Check Approved | 2/3/2020 | JESSE VIDUYA |
| Issued | 2/27/2020 | LADBS |
| OK for CofC | 12/18/2024 | GRANT WOODS |
| CofC Issued | 12/31/2024 | DAVID TSAU |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 2/24/2020 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Built Development Corporation; Lic. No.: 991996-B | 12400 WILSHIRE BLVD STE 230 LOS ANGELES, CA 90025 |
| Engineer | Hassan,, Mohamed Ali; Lic. No.: S5285 | 3621 HARBOR BLVD #125 SANTA ANA, CA 92704 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/30/2020 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 7/1/2020 | Partial Approval | PAUL DAVIDSON |
| Deputy Reinf. Concrete | 7/2/2020 | Conditional Approval | TED RIES |
| Deputy Steel/Welding | 7/23/2020 | Conditional Approval | GRANT WOODS |
| Deputy Steel/Welding | 7/30/2020 | Conditional Approval | GRANT WOODS |
| Footing/Foundation/Slab | 9/17/2020 | Not Ready for Inspection | JOHN DODGE |
| Structural Steel Frame | 9/17/2020 | Approved | JOHN DODGE |
| Footing/Foundation/Slab | 9/25/2020 | Approved | JONATHAN QUACH |
| Deputy Reinf. Concrete | 9/29/2020 | Conditional Approval | GRANT WOODS |
| Deputy Reinf. Concrete | 9/30/2020 | Conditional Approval | GRANT WOODS |
| Wood Frame | 10/7/2020 | Approved | GRANT WOODS |
| Interior/Exterior Lathing | 10/14/2020 | Approved | RUSSELL BONVOULOIR |
| Final | 11/10/2020 | Corrections Issued | JOHN DODGE |
| SGSOV-Seismic Gas S/O Valve | 11/10/2020 | SGSOV Not Ready | JOHN DODGE |
| Smoke Detectors | 11/10/2020 | Not Ready for Inspection | JOHN DODGE |
| Final | 10/4/2021 | Not Ready for Inspection | JOHN DODGE |
| SGSOV-Seismic Gas S/O Valve | 10/4/2021 | SGSOV Not Ready | JOHN DODGE |
| Smoke Detectors | 10/4/2021 | Not Ready for Inspection | JOHN DODGE |
| Final | 6/5/2024 | Not Ready for Inspection | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 6/5/2024 | SGSOV Not Ready | GRANT WOODS |
| Smoke Detectors | 6/5/2024 | Not Ready for Inspection | GRANT WOODS |
| Final | 12/18/2024 | OK for CofC | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 12/18/2024 | SGSOV Approved | GRANT WOODS |
| Smoke Detectors | 12/18/2024 | Approved | GRANT WOODS |