2129 N WOLLAM ST 90065
Certificate Information: 2129 N WOLLAM ST 90065
- Application / Permit
- 19016-10000-37782
- Plan Check / Job No.
- B19LA24888
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL TO (E) SINGLE FAMILY DWELLING. REMODEL BATHROOMS.
- Permit Issued
- Issued on 7/28/2020
- Issuing Office
- Current Status
- Permit Finaled on 12/30/2020
Permit Application Status History
| Plan Check Approved | 11/21/2019 | KEVIN MORALES |
| Issued | 7/28/2020 | APPLICANT |
| Building Plans Picked Up | 7/29/2020 | APPLICANT |
| Permit Finaled | 12/29/2020 | HAMIK HARTOUNIAN |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Zorzoli Construction Inc; Lic. No.: 965210-B | 19903 EAST RAMBLING ROAD COVINA, CA 91724 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 8/20/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 8/20/2020 | Partial Approval | HAMIK HARTOUNIAN |
| HVAC-Rough | 8/20/2020 | Partial Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 8/20/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 9/1/2020 | Partial Approval | HAMIK HARTOUNIAN |
| HVAC-Rough | 9/1/2020 | Partial Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 9/1/2020 | Partial Approval | HAMIK HARTOUNIAN |
| Wood Frame | 9/1/2020 | Partial Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 9/28/2020 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 9/28/2020 | Partial Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 9/28/2020 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 9/28/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 9/28/2020 | Approved | HAMIK HARTOUNIAN |
| Shower Pan | 9/28/2020 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 10/8/2020 | Approved | HAMIK HARTOUNIAN |
| Insulation | 10/8/2020 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 10/8/2020 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 12/17/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| Final | 12/17/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Final | 12/17/2020 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Final | 12/17/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 12/17/2020 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 12/17/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 12/29/2020 | Approved | HAMIK HARTOUNIAN |
| Final | 12/29/2020 | Permit Finaled | HAMIK HARTOUNIAN |
| HVAC-Final | 12/29/2020 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Final | 12/29/2020 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 12/29/2020 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 12/29/2020 | Approved | HAMIK HARTOUNIAN |