CONVERTING OFFICE ROOM (208 sf) IN (E) SFD TO AN ATTACHED ACCESSORY DWELLING UNIT (ADU) PER ORDINANCE. ***SEE COMMENTS*** 1 OF 5
Permit Issued
Issued on 3/3/2022
Issuing Office
Current Status
Permit Finaled on 5/4/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/20/2019 APPLICANT
Assigned to Plan Check Engineer 12/13/2019 MICHAEL LOPEZ
Corrections Issued 12/24/2019 MIGUEL JIMENEZ
Quality Review Completed 12/27/2019 BILL STUTSMAN
Applicant returned to address corrections 12/14/2021 MICHAEL LOPEZ
Applicant returned to address corrections 2/7/2022 MICHAEL LOPEZ
Applicant returned to address corrections 2/8/2022 MICHAEL LOPEZ
Plan Check Approved 2/22/2022 MICHAEL LOPEZ
Issued 3/3/2022 APPLICANT
Building Plans Picked Up 3/9/2022 APPLICANT
Permit Finaled 5/4/2026 NICHOLAS LOPEZ

Permit Application Clearance Information

Tract Map conditions Cleared 1/13/2020 ANNA VIDAL
Address approval Cleared 1/17/2020 ELENA LOPEZ
Eng Process Fee Ord 176,300 Cleared 1/17/2020 ELENA LOPEZ
Sewer availability Cleared 1/17/2020 ELENA LOPEZ
Miscellaneous Cleared 1/23/2020 SAM NAVID
Miscellaneous Cleared 10/26/2021 MARITZA PRZEKOP

Contact Information

Architect Storey,, Simon Joseph; Lic. No.: C35346 1416 FAIRBANKS PLACE      LOS ANGELES, CA 90026
Contractor Owner-Builder       ,
Engineer Simonian, Ara; Lic. No.: C37208 314 E BROADWAY STE A      GLENDALE, CA 91205

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/16/2022 Corrections Issued STUART CHAPMAN
Wood Frame 4/5/2022 Corrections Issued SCOTT FINNILA
Wood Frame 5/13/2022 Approved STUART CHAPMAN
Insulation 5/19/2022 Approved SCOTT FINNILA
Drywall Nailing 6/1/2022 Approved SCOTT FINNILA
Pre-Inspection 7/10/2025 Partial Inspection BRENDAN MORELLI
Pre-Inspection 7/28/2025 No Access for Inspection BRENDAN MORELLI
Pre-Inspection 7/31/2025 Corrections Issued BRENDAN MORELLI
Final 8/27/2025 Not Ready for Inspection BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 8/27/2025 SGSOV Approved BRENDAN MORELLI
Smoke Detectors 8/27/2025 Approved BRENDAN MORELLI
Final 9/10/2025 Not Ready for Inspection BRENDAN MORELLI
Final 9/22/2025 Partial Approval BRENDAN MORELLI
Final 5/4/2026 Permit Finaled NICHOLAS LOPEZ