2639 N VERMONT AVE 90027
Certificate Information: 2639 N VERMONT AVE 90027
- Application / Permit
- 19016-10000-37407
- Plan Check / Job No.
- B19LA24643
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED INTERIOR ALTERATION TO REMODEL KITCHEN AND BEDROOM AREA; WORK TO INCLUDE REMOVING A WALL AND REPLACING WITH BEAM AND POSTS AND CHANGING FLOOR LAYOUT
- Permit Issued
- Issued on 1/16/2020
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 11/16/2020
Permit Application Status History
| Submitted | 11/20/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/20/2019 | SINA KHOSRAVI |
| Corrections Issued | 11/20/2019 | SINA KHOSRAVI |
| Plan Check Approved | 12/6/2019 | SINA KHOSRAVI |
| Issued | 1/16/2020 | LADBS |
| Permit Finaled | 11/16/2020 | DONALD CRICHLOW |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 11/20/2019 | KIRK LINKLATER |
Contact Information
| Contractor | True Building Inc; Lic. No.: 938015-B | 1064 MYRA AVE LOS ANGELES, CA 90029 |
| Engineer | Lam,, Chsung Say; Lic. No.: C78287 | 6919 THELMA AVE BUENA PARK, CA 90620 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/10/2020 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 6/25/2020 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 6/25/2020 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 6/25/2020 | Partial Approval | JOSEPH MCGARRY |
| Insulation | 6/25/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| PLUMBING-Rough | 6/25/2020 | Approved | JOSEPH MCGARRY |
| Insulation | 7/7/2020 | Approved | ARTHUR SARGSYAN |
| Interior/Exterior Lathing | 7/7/2020 | Approved | ARTHUR SARGSYAN |
| Wood Frame | 7/7/2020 | Approved | ARTHUR SARGSYAN |
| Drywall Nailing | 7/13/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 10/1/2020 | Partial Inspection | DONALD CRICHLOW |
| SGSOV-Seismic Gas S/O Valve | 10/1/2020 | SGSOV Approved | DONALD CRICHLOW |
| Smoke Detectors | 10/1/2020 | Not Ready for Inspection | DONALD CRICHLOW |
| Final | 11/16/2020 | Permit Finaled | DONALD CRICHLOW |
| Smoke Detectors | 11/16/2020 | Approved | DONALD CRICHLOW |