160 N GLENDALE BLVD 90026
Certificate Information: 160 N GLENDALE BLVD 90026
- Application / Permit
- 19016-10000-37289
- Plan Check / Job No.
- B19LA24574
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (12) Manufacturing
- Work Description
- (URM)SEISMIC UPGRADE PER APPENDIX A1 INCLUDE SHOTCRETE AT PORTONS OF REAR WALL AND DRAGS AT REAR WALL AND ADD CHORDS ALONG BOTH LONG SIDES OF BLDG <<NO IMPACT TOOLS ALLOWED>><<CHANGE OF USE UNDER SEPARATED SUBMITTAL>>
- Permit Issued
- Issued on 4/1/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/18/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2019 | DEAN LEE |
| Corrections Issued | 11/27/2019 | DEAN LEE |
| Quality Review Completed | 12/2/2019 | BILL STUTSMAN |
| Building Plans Picked Up | 12/5/2019 | APPLICANT |
| Applicant returned to address corrections | 1/8/2020 | DEAN LEE |
| Plan Check Approved | 1/28/2020 | DEAN LEE |
| Issued | 4/1/2020 | LADBS |
| CofO in Progress | 4/1/2024 | RONALD JIMENEZ |
| CofO Issued | 4/1/2024 | ERNESTO CORRAL |
| Permit Finaled | 4/1/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Gardner Austin Building Corporation; Lic. No.: 779293-B | 25251 AVENUE TIBBITTS VALENCIA, CA 91355 |
| Engineer | Carpenter,, Lauren D; Lic. No.: S2511 | 350 S FIGUEROA ST 400 LOS ANGELES, CA 90071 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/16/2020 | Approved | KATY RAMIREZ |
| Deputy Drilled-In Anchors | 2/4/2021 | Conditional Approval | DANIEL COLLINS |
| Deputy Drilled-In Anchors | 6/2/2021 | Conditional Approval | DANIEL COLLINS |
| Deputy Reinf. Concrete | 6/2/2021 | Conditional Approval | DANIEL COLLINS |
| Deputy Drilled-In Anchors | 6/3/2021 | Conditional Approval | DANIEL COLLINS |
| Deputy Reinf. Concrete | 6/3/2021 | Conditional Approval | DANIEL COLLINS |
| Deputy Drilled-In Anchors | 6/4/2021 | Conditional Approval | DANIEL COLLINS |
| Deputy Reinf. Concrete | 6/4/2021 | Conditional Approval | DANIEL COLLINS |
| Deputy Reinf. Concrete | 6/7/2021 | Conditional Approval | KATY RAMIREZ |
| Deputy Reinf. Concrete | 6/8/2021 | Conditional Approval | KATY RAMIREZ |
| Deputy Reinf. Concrete | 6/9/2021 | Conditional Approval | KATY RAMIREZ |
| Deputy Reinf. Concrete | 6/14/2021 | Conditional Approval | DANIEL COLLINS |
| Final | 5/25/2022 | Partial Approval | JONATHAN QUACH |
| METHANE-Final | 5/25/2022 | Approved | JONATHAN QUACH |
| SGSOV-Seismic Gas S/O Valve | 5/25/2022 | SGSOV Approved | JONATHAN QUACH |
| Smoke Detectors | 5/25/2022 | Approved | JONATHAN QUACH |
| Final | 3/27/2024 | Not Ready for Inspection | RONALD JIMENEZ |
| Final | 3/29/2024 | Conditional Approval | RONALD JIMENEZ |
| Final | 4/1/2024 | OK to Issue CofO | RONALD JIMENEZ |