160 N GLENDALE BLVD 90026

Certificate Information: 160 N GLENDALE BLVD 90026

Application / Permit
19016-10000-37289
Plan Check / Job No.
B19LA24574
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(12) Manufacturing
Work Description
(URM)SEISMIC UPGRADE PER APPENDIX A1 INCLUDE SHOTCRETE AT PORTONS OF REAR WALL AND DRAGS AT REAR WALL AND ADD CHORDS ALONG BOTH LONG SIDES OF BLDG <<NO IMPACT TOOLS ALLOWED>><<CHANGE OF USE UNDER SEPARATED SUBMITTAL>>
Permit Issued
Issued on 4/1/2020
Issuing Office
Metro
Current Status
CofO Issued on 4/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/18/2019 APPLICANT
Assigned to Plan Check Engineer 11/21/2019 DEAN LEE
Corrections Issued 11/27/2019 DEAN LEE
Quality Review Completed 12/2/2019 BILL STUTSMAN
Building Plans Picked Up 12/5/2019 APPLICANT
Applicant returned to address corrections 1/8/2020 DEAN LEE
Plan Check Approved 1/28/2020 DEAN LEE
Issued 4/1/2020 LADBS
CofO in Progress 4/1/2024 RONALD JIMENEZ
CofO Issued 4/1/2024 ERNESTO CORRAL
Permit Finaled 4/1/2024 ERNESTO CORRAL

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Gardner Austin Building Corporation; Lic. No.: 779293-B 25251 AVENUE TIBBITTS      VALENCIA, CA 91355
Engineer Carpenter,, Lauren D; Lic. No.: S2511 350 S FIGUEROA ST 400      LOS ANGELES, CA 90071

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/16/2020 Approved KATY RAMIREZ
Deputy Drilled-In Anchors 2/4/2021 Conditional Approval DANIEL COLLINS
Deputy Drilled-In Anchors 6/2/2021 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 6/2/2021 Conditional Approval DANIEL COLLINS
Deputy Drilled-In Anchors 6/3/2021 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 6/3/2021 Conditional Approval DANIEL COLLINS
Deputy Drilled-In Anchors 6/4/2021 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 6/4/2021 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 6/7/2021 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 6/8/2021 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 6/9/2021 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 6/14/2021 Conditional Approval DANIEL COLLINS
Final 5/25/2022 Partial Approval JONATHAN QUACH
METHANE-Final 5/25/2022 Approved JONATHAN QUACH
SGSOV-Seismic Gas S/O Valve 5/25/2022 SGSOV Approved JONATHAN QUACH
Smoke Detectors 5/25/2022 Approved JONATHAN QUACH
Final 3/27/2024 Not Ready for Inspection RONALD JIMENEZ
Final 3/29/2024 Conditional Approval RONALD JIMENEZ
Final 4/1/2024 OK to Issue CofO RONALD JIMENEZ