1915 S SAN PEDRO ST 90011
Certificate Information: 1915 S SAN PEDRO ST 90011
- Application / Permit
- 19016-10000-37201
- Plan Check / Job No.
- B19LA24522
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (22) Warehouse
- Work Description
- REINFORCE (E) WOOD TRUSSES BY ADDING 8 HSS STEEL COLUMNS W/ NEW PAD FOOTINGS. CLOSE (E) OPENINGS. ADD ONE NEW DISABLE BATHROOM.
- Permit Issued
- Issued on 3/10/2020
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 3/2/2021
Permit Application Status History
| Submitted | 11/18/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/12/2019 | CHUNG-WEN CHUANG |
| Corrections Issued | 1/2/2020 | CHUNG-WEN CHUANG |
| Disabled Access Plans Picked Up | 1/13/2020 | APPLICANT |
| Quality Review Completed | 1/16/2020 | KESETE HAREGOT |
| Building Plans Picked Up | 1/23/2020 | APPLICANT |
| Applicant returned to address corrections | 2/11/2020 | CHUNG-WEN CHUANG |
| Plan Check Approved | 3/10/2020 | CHUNG-WEN CHUANG |
| Issued | 3/10/2020 | LADBS |
| Permit Finaled | 3/1/2021 | DANIEL COLLINS |
Permit Application Clearance Information
| DAS Clearance | Cleared | 2/12/2020 | ELIZABETH TOMS |
| Redevelopment Project Area | Cleared | 3/9/2020 | DAVID URITA |
| Hold | Cleared | 4/1/2020 | JEREMY CORONEL |
Contact Information
| Contractor | California Building Innovation Inc; Lic. No.: 1026936-B | 1407 N BATAVIA ST STE 113 ORANGE, CA 92867 |
| Engineer | Mohazzab, Hosseinian, Hossein Jon; Lic. No.: S3760 | 5408 W 140TH ST HAWTHORNE, CA 90250 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/3/2020 | Partial Approval | DANIEL COLLINS |
| Footing/Foundation/Slab | 4/3/2020 | Not Ready for Inspection | DANIEL COLLINS |
| Wood Frame | 4/3/2020 | Corrections Issued | DANIEL COLLINS |
| Excavation/Setback/Form/Re-Bar | 4/28/2020 | Partial Approval | DANIEL COLLINS |
| Wood Frame | 4/28/2020 | Partial Approval | DANIEL COLLINS |
| Wood Frame | 11/19/2020 | Partial Approval | DANIEL COLLINS |
| Drywall Nailing | 11/23/2020 | Approved | DANIEL COLLINS |
| Final | 1/12/2021 | Not Ready for Inspection | DANIEL COLLINS |
| SGSOV-Seismic Gas S/O Valve | 1/12/2021 | SGSOV Approved | DANIEL COLLINS |
| Smoke Detectors | 1/12/2021 | Approved | DANIEL COLLINS |
| Final | 3/1/2021 | Permit Finaled | DANIEL COLLINS |