2304 S HALM AVE 90034
Certificate Information: 2304 S HALM AVE 90034
- Application / Permit
- 19016-10000-37159
- Plan Check / Job No.
- B19LA24500
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH 93. INSTALL 1 (N) Special Cantilever Column
- Permit Issued
- Issued on 5/10/2022
- Issuing Office
- Metro
- Current Status
- CofC Issued on 11/29/2022
Permit Application Status History
| Submitted | 11/18/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/11/2019 | JESSE VIDUYA |
| Corrections Issued | 12/18/2019 | JESSE VIDUYA |
| Quality Review Completed | 12/18/2019 | HANS SANTIAGO |
| Building Plans Picked Up | 12/31/2019 | APPLICANT |
| Applicant returned to address corrections | 3/4/2020 | JESSE VIDUYA |
| Plan Check Approved | 3/16/2020 | JESSE VIDUYA |
| Issued | 5/10/2022 | APPLICANT |
| OK for CofC | 11/23/2022 | PAUL DAVIDSON |
| CofC Issued | 11/29/2022 | HENRY BAGHDASSARIAN |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 4/13/2022 | MICHAEL SOTO |
Contact Information
| Contractor | Sks Construction; Lic. No.: 720390-B | 15134 FRIAR STREET VAN NUYS, CA 91411 |
| Engineer | Shaolian,, Shahab Joseph; Lic. No.: C84155 | 5104 GARDEN GROVE TARZANA, CA 91356 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/22/2022 | Partial Inspection | PAUL DAVIDSON |
| Deputy Drilled-In Anchors | 6/28/2022 | Conditional Approval | PAUL DAVIDSON |
| Deputy Reinf. Concrete | 6/29/2022 | Conditional Approval | PAUL DAVIDSON |
| Deputy Steel/Welding | 6/29/2022 | Conditional Approval | PAUL DAVIDSON |
| Footing/Foundation/Slab | 6/29/2022 | Approved | PAUL DAVIDSON |
| Structural Steel Frame | 6/29/2022 | Approved | PAUL DAVIDSON |
| Wood Frame | 6/29/2022 | Approved | PAUL DAVIDSON |
| Deputy Reinf. Concrete | 6/30/2022 | Conditional Approval | PAUL DAVIDSON |
| Interior/Exterior Lathing | 7/20/2022 | Approved | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 11/18/2022 | SGSOV Not Ready | PAUL DAVIDSON |
| Final | 11/23/2022 | OK for CofC | PAUL DAVIDSON |
| SGSOV-Seismic Gas S/O Valve | 11/23/2022 | SGSOV Approved | PAUL DAVIDSON |
| Smoke Detectors | 11/23/2022 | Approved | PAUL DAVIDSON |