6990 S BUDLONG AVE 90044
Certificate Information: 6990 S BUDLONG AVE 90044
- Application / Permit
- 19016-10000-37063
- Plan Check / Job No.
- B19LA24449
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 22'X24' DETACHED GARAGE INTO ADU. CONSTRUCTION BY WFPP. "COMPLY WITH DEPARTMENT ORDER EFFECTIVE DATE 08/30/2019. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 6/9/2021
- Issuing Office
- Current Status
- CofO Issued on 10/21/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/15/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/5/2019 | CHUNG-WEN CHUANG |
| Corrections Issued | 12/10/2019 | MIGUEL JIMENEZ |
| Quality Review Completed | 12/16/2019 | BILL STUTSMAN |
| Green Plans Picked Up | 12/30/2019 | APPLICANT |
| Applicant returned to address corrections | 6/11/2020 | CHUNG-WEN CHUANG |
| Applicant returned to address corrections | 6/17/2020 | CHUNG-WEN CHUANG |
| Applicant returned to address corrections | 2/8/2021 | CHUNG-WEN CHUANG |
| Plan Check Approved | 4/29/2021 | CHUNG-WEN CHUANG |
| Issued | 6/9/2021 | APPLICANT |
| Building Plans Picked Up | 6/15/2021 | APPLICANT |
| CofO in Progress | 6/26/2024 | JOHN PARKER |
| Permit Finaled | 10/21/2024 | CLAUDIO MORENO |
| CofO Issued | 10/21/2024 | CLAUDIO MORENO |
| Permit Finaled | 10/21/2024 | CLAUDIO MORENO |
Permit Application Clearance Information
| Address approval | Cleared | 2/6/2020 | JUAN ASHTON |
| Sewer availability | Cleared | 2/6/2020 | JUAN ASHTON |
| Eng Process Fee Ord 176,300 | Cleared | 2/10/2020 | JUAN ASHTON |
| Green Code | Cleared | 2/10/2020 | MIGUEL JIMENEZ |
| Construction near power lines | Cleared | 7/18/2020 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN PARKER, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICHAEL SERETTI, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| HECTOR RODRIGUEZ, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| BRUCE TODD, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAVIER RAMOS SR, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIAN PODPORA, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/1/2022 | Not Ready for Inspection | ANDEY CHAPARRO |
| Footing/Foundation/Slab | 7/1/2022 | Corrections Issued | ANDEY CHAPARRO |
| Pre-Inspection | 7/7/2022 | Partial Approval | ANDEY CHAPARRO |
| Footing/Foundation/Slab | 8/5/2022 | Partial Approval | ANDEY CHAPARRO |
| Pre-Inspection | 2/13/2023 | Partial Inspection | DANIEL GONZALEZ |
| ELECTRICAL-Rough | 6/2/2023 | Approved | JOHN PARKER |
| PLUMBING-Rough | 6/2/2023 | Corrections Issued | JOHN PARKER |
| Sewer | 6/2/2023 | Corrections Issued | JOHN PARKER |
| Insulation | 6/30/2023 | Approved | JOHN PARKER |
| PLUMBING-Rough | 6/30/2023 | Approved | JOHN PARKER |
| Sewer | 6/30/2023 | Approved | JOHN PARKER |
| Drywall Nailing | 9/8/2023 | Approved | JOHN PARKER |
| Green Building Rough | 9/8/2023 | Approved | JOHN PARKER |
| Interior/Exterior Lathing | 10/6/2023 | Approved | JOHN PARKER |
| ELECTRICAL-Rough | 2/16/2024 | Approved | JOHN PARKER |
| Service/Power Release | 2/16/2024 | Approved | JOHN PARKER |
| BUILDING-Rough-Frame | 6/11/2024 | Approved | JOHN PARKER |
| Final | 6/11/2024 | OK to Issue CofO | JOHN PARKER |
| Green Building Final | 6/11/2024 | Approved | JOHN PARKER |
| SGSOV-Seismic Gas S/O Valve | 6/11/2024 | SGSOV Approved | JOHN PARKER |
| Smoke Detectors | 6/11/2024 | Approved | JOHN PARKER |