6990 S BUDLONG AVE 90044

Certificate Information: 6990 S BUDLONG AVE 90044

Application / Permit
19016-10000-37063
Plan Check / Job No.
B19LA24449
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 22'X24' DETACHED GARAGE INTO ADU. CONSTRUCTION BY WFPP. "COMPLY WITH DEPARTMENT ORDER EFFECTIVE DATE 08/30/2019. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 6/9/2021
Issuing Office
Current Status
CofO Issued on 10/21/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/15/2019 APPLICANT
Assigned to Plan Check Engineer 12/5/2019 CHUNG-WEN CHUANG
Corrections Issued 12/10/2019 MIGUEL JIMENEZ
Quality Review Completed 12/16/2019 BILL STUTSMAN
Green Plans Picked Up 12/30/2019 APPLICANT
Applicant returned to address corrections 6/11/2020 CHUNG-WEN CHUANG
Applicant returned to address corrections 6/17/2020 CHUNG-WEN CHUANG
Applicant returned to address corrections 2/8/2021 CHUNG-WEN CHUANG
Plan Check Approved 4/29/2021 CHUNG-WEN CHUANG
Issued 6/9/2021 APPLICANT
Building Plans Picked Up 6/15/2021 APPLICANT
CofO in Progress 6/26/2024 JOHN PARKER
Permit Finaled 10/21/2024 CLAUDIO MORENO
CofO Issued 10/21/2024 CLAUDIO MORENO
Permit Finaled 10/21/2024 CLAUDIO MORENO

Permit Application Clearance Information

Address approval Cleared 2/6/2020 JUAN ASHTON
Sewer availability Cleared 2/6/2020 JUAN ASHTON
Eng Process Fee Ord 176,300 Cleared 2/10/2020 JUAN ASHTON
Green Code Cleared 2/10/2020 MIGUEL JIMENEZ
Construction near power lines Cleared 7/18/2020 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN PARKER, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
MICHAEL SERETTI, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
HECTOR RODRIGUEZ, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
BRUCE TODD, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
JAVIER RAMOS SR, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
MARIAN PODPORA, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/1/2022 Not Ready for Inspection ANDEY CHAPARRO
Footing/Foundation/Slab 7/1/2022 Corrections Issued ANDEY CHAPARRO
Pre-Inspection 7/7/2022 Partial Approval ANDEY CHAPARRO
Footing/Foundation/Slab 8/5/2022 Partial Approval ANDEY CHAPARRO
Pre-Inspection 2/13/2023 Partial Inspection DANIEL GONZALEZ
ELECTRICAL-Rough 6/2/2023 Approved JOHN PARKER
PLUMBING-Rough 6/2/2023 Corrections Issued JOHN PARKER
Sewer 6/2/2023 Corrections Issued JOHN PARKER
Insulation 6/30/2023 Approved JOHN PARKER
PLUMBING-Rough 6/30/2023 Approved JOHN PARKER
Sewer 6/30/2023 Approved JOHN PARKER
Drywall Nailing 9/8/2023 Approved JOHN PARKER
Green Building Rough 9/8/2023 Approved JOHN PARKER
Interior/Exterior Lathing 10/6/2023 Approved JOHN PARKER
ELECTRICAL-Rough 2/16/2024 Approved JOHN PARKER
Service/Power Release 2/16/2024 Approved JOHN PARKER
BUILDING-Rough-Frame 6/11/2024 Approved JOHN PARKER
Final 6/11/2024 OK to Issue CofO JOHN PARKER
Green Building Final 6/11/2024 Approved JOHN PARKER
SGSOV-Seismic Gas S/O Valve 6/11/2024 SGSOV Approved JOHN PARKER
Smoke Detectors 6/11/2024 Approved JOHN PARKER