11105 W ROSE AVE 90034
Certificate Information: 11105 W ROSE AVE 90034
- Application / Permit
- 19016-10000-37059
- Plan Check / Job No.
- B19LA24447
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH. 93. INSTALL (2) SCCS/PLYWOOD SHEARWALL.
- Permit Issued
- Issued on 1/24/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 8/12/2020
Permit Application Status History
| Submitted | 11/15/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/4/2019 | JESSE VIDUYA |
| Corrections Issued | 12/10/2019 | JESSE VIDUYA |
| Quality Review Completed | 12/12/2019 | HANS SANTIAGO |
| Building Plans Picked Up | 12/16/2019 | APPLICANT |
| Plan Check Approved | 1/13/2020 | JESSE VIDUYA |
| Issued | 1/24/2020 | LADBS |
| OK for CofC | 8/11/2020 | GRANT WOODS |
| CofC Issued | 8/12/2020 | TED RIES |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 12/13/2019 | CHARLES GARCIA |
Contact Information
| Contractor | Quakestrong; Lic. No.: 1037437-B | 1213 LA BREA AVENUE LOS ANGELES, CA 90019 |
| Engineer | Erdelyi,, Peter Tibor; Lic. No.: C26962 | 1950 SAWTELLE BLVD STE 175 LOS ANGELES, CA 90025 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/7/2020 | Approved | GRANT WOODS |
| Deputy Drilled-In Anchors | 6/18/2020 | Conditional Approval | GRANT WOODS |
| Deputy Steel/Welding | 6/24/2020 | Conditional Approval | PAUL DAVIDSON |
| Footing/Foundation/Slab | 6/30/2020 | Approved | SORIN CIRSTOIU |
| Structural Steel Frame | 6/30/2020 | Partial Approval | SORIN CIRSTOIU |
| Wood Frame | 6/30/2020 | Partial Inspection | SORIN CIRSTOIU |
| Deputy Reinf. Concrete | 7/2/2020 | Conditional Approval | SORIN CIRSTOIU |
| Structural Steel Frame | 7/8/2020 | Partial Approval | GRANT WOODS |
| Wood Frame | 7/8/2020 | Partial Approval | GRANT WOODS |
| Deputy Wood Construction | 7/10/2020 | Conditional Approval | GRANT WOODS |
| Structural Steel Frame | 7/13/2020 | Not Ready for Inspection | GRANT WOODS |
| Wood Frame | 7/13/2020 | Partial Inspection | GRANT WOODS |
| Structural Steel Frame | 7/15/2020 | Approved | GRANT WOODS |
| Wood Frame | 7/15/2020 | Approved | GRANT WOODS |
| Interior/Exterior Lathing | 7/17/2020 | Approved | GRANT WOODS |
| Final | 8/11/2020 | OK for CofC | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 8/11/2020 | SGSOV Approved | GRANT WOODS |
| Smoke Detectors | 8/11/2020 | Approved | GRANT WOODS |