1281 S FEDERAL AVE 90025
Certificate Information: 1281 S FEDERAL AVE 90025
- Application / Permit
- 19016-10000-36754
- Plan Check / Job No.
- B19LA24224
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH. 93. INSTALL (3) SCCS.
- Permit Issued
- Issued on 8/31/2020
- Issuing Office
- Current Status
- CofC Issued on 10/8/2021
Permit Application Status History
| Submitted | 11/13/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/12/2019 | DANIEL YIP |
| Corrections Issued | 12/16/2019 | DANIEL YIP |
| Quality Review Completed | 12/17/2019 | HANS SANTIAGO |
| Building Plans Picked Up | 12/18/2019 | APPLICANT |
| Plan Check Approved | 1/17/2020 | DANIEL YIP |
| Issued | 8/31/2020 | APPLICANT |
| OK for CofC | 10/6/2021 | GRANT WOODS |
| CofC Issued | 10/8/2021 | TED RIES |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 8/17/2020 | STEVEN HOFSTAD |
Contact Information
| Contractor | Optimum Seismic Inc; Lic. No.: 1012702-B | 5508 S SANTA FE AVENUE VERNON, CA 90058 |
| Engineer | Mirmohammadsadeghi,, Kamaleddin; Lic. No.: C53468 | 1377 S BEVERLY GLEN BLVD 308 LOS ANGELES, CA 90024 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/4/2020 | Not Ready for Inspection | JOHN DODGE |
| Pre-Inspection | 9/9/2020 | Corrections Issued | GRANT WOODS |
| Deputy Drilled-In Anchors | 9/30/2020 | Conditional Approval | GRANT WOODS |
| Footing/Foundation/Slab | 10/2/2020 | Approved | GRANT WOODS |
| Structural Steel Frame | 10/2/2020 | Approved | GRANT WOODS |
| Wood Frame | 10/2/2020 | Approved | GRANT WOODS |
| Deputy Reinf. Concrete | 10/5/2020 | Conditional Approval | GRANT WOODS |
| Pre-Inspection | 12/8/2020 | Partial Inspection | JOHN DODGE |
| Footing/Foundation/Slab | 1/20/2021 | Approved | GRANT WOODS |
| Structural Steel Frame | 1/20/2021 | Approved | GRANT WOODS |
| Interior/Exterior Lathing | 2/5/2021 | Not Ready for Inspection | PAUL DAVIDSON |
| Interior/Exterior Lathing | 2/10/2021 | Approved | GRANT WOODS |
| Final | 6/25/2021 | Corrections Issued | GRANT WOODS |
| METHANE-Final | 6/25/2021 | Approved | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 6/25/2021 | SGSOV Not Ready | GRANT WOODS |
| Smoke Detectors | 6/25/2021 | Approved | GRANT WOODS |
| Final | 10/6/2021 | OK for CofC | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 10/6/2021 | SGSOV Approved | GRANT WOODS |