7310 W 89TH ST 90045

Certificate Information: 7310 W 89TH ST 90045

Application / Permit
19016-10000-36483
Plan Check / Job No.
B19LA24076
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERTING AN (E) DETACHED GARAGE AND STORAGE IN TO AN ACCESSORY DWELING UNIT WITH LAUNDRY ROOM PER AB 494 AND SB 299
Permit Issued
Issued on 1/22/2020
Issuing Office
Metro
Current Status
CofO Issued on 9/8/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/12/2019 APPLICANT
Assigned to Plan Check Engineer 11/15/2019 MONICA RAMIREZ
Corrections Issued 11/15/2019 MONICA RAMIREZ
Plan Check Approved 1/22/2020 SHANGQIN XIE
Issued 1/22/2020 LADBS
CofO in Progress 8/10/2020 JUAN VALENZUELA
CofO Issued 9/8/2020 VINCENT COTTON
Permit Finaled 9/8/2020 VINCENT COTTON

Permit Application Clearance Information

Address approval Cleared 11/18/2019 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 11/18/2019 CELINA MORENO
Grading Pre-Inspection Cleared 11/18/2019 PATRICK MISCHLICH
Sewer availability Cleared 11/18/2019 CELINA MORENO
Specific Plan Cleared 11/18/2019 ANNA VIDAL
Construction near power lines Cleared 1/22/2020 WALTER RAMIREZ
Construction within easement Cleared 1/22/2020 WALTER RAMIREZ

Contact Information

Contractor Levet Inc; Lic. No.: 1027447-B 1110 SONORA AVE #101      GLENDALE, CA 91201
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/3/2020 Corrections Issued DAVID FEILER
Underground Mechanical 2/3/2020 Partial Approval DAVID FEILER
Excavation/Setback/Form/Re-Bar 3/9/2020 Approved JUAN VALENZUELA
ELECTRICAL-Rough 3/25/2020 Corrections Issued JUAN VALENZUELA
PLUMBING-Rough 3/25/2020 Corrections Issued JUAN VALENZUELA
Wood Frame 3/25/2020 Corrections Issued JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 4/13/2020 Partial Approval JUAN VALENZUELA
PLUMBING-Rough 4/13/2020 Approved JUAN VALENZUELA
Special/Order Compliance 4/13/2020 Approved JUAN VALENZUELA
ELECTRICAL-Rough 5/19/2020 Corrections Issued JOHNNY MIRANDA
Interior/Exterior Lathing 5/19/2020 Partial Approval JOHNNY MIRANDA
Wood Frame 5/19/2020 Approved JOHNNY MIRANDA
ELECTRICAL-Final 5/20/2020 Approved DAVID HEINE
Drywall Nailing 6/3/2020 Approved JUAN VALENZUELA
Interior/Exterior Lathing 6/3/2020 Not Ready for Inspection JUAN VALENZUELA
BUILDING-Rough-Frame 7/29/2020 Approved JUAN VALENZUELA
ELECTRICAL-Final 7/29/2020 Corrections Issued JUAN VALENZUELA
Final 7/29/2020 Not Ready for Inspection JUAN VALENZUELA
Green Building Final 7/29/2020 Approved JUAN VALENZUELA
Green Building Rough 7/29/2020 Approved JUAN VALENZUELA
HVAC-Final 7/29/2020 Approved JUAN VALENZUELA
PLUMBING-Final 7/29/2020 Corrections Issued JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 7/29/2020 SGSOV Not Ready JUAN VALENZUELA
Smoke Detectors 7/29/2020 Not Ready for Inspection JUAN VALENZUELA
ELECTRICAL-Final 8/10/2020 Approved JUAN VALENZUELA
Final 8/10/2020 OK to Issue CofO JUAN VALENZUELA
PLUMBING-Final 8/10/2020 Approved JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 8/10/2020 SGSOV Approved JUAN VALENZUELA
Service/Power Release 8/10/2020 Approved JUAN VALENZUELA
Smoke Detectors 8/10/2020 Approved JUAN VALENZUELA