5667 W LA MIRADA AVE 90038

Certificate Information: 5667 W LA MIRADA AVE 90038

Application / Permit
19016-10000-36269
Plan Check / Job No.
B19LA23972
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT AS PER LABC CH 93. INSTALL 1 OMF AND 1 SCCS.
Permit Issued
Issued on 2/20/2020
Issuing Office
Metro
Current Status
CofC Issued on 6/18/2020

Permit Application Status History

Submitted 11/8/2019 APPLICANT
Assigned to Plan Check Engineer 11/26/2019 JOHN FRANCIA
Corrections Issued 12/3/2019 JOHN FRANCIA
Quality Review Completed 12/4/2019 SAI KHUM
Building Plans Picked Up 12/23/2019 APPLICANT
Plan Check Approved 2/20/2020 JOHN FRANCIA
Issued 2/20/2020 LADBS
OK for CofC 6/17/2020 FELIX CEBALLOS
CofC Issued 6/18/2020 ERNESTO CORRAL

Permit Application Clearance Information

Historic Resource Verification Cleared 1/6/2020 GISELLE CORELLA
Redevelopment Project Area Cleared 1/6/2020 GISELLE CORELLA
Housing rent stabilization Cleared 2/20/2020 ISMAEL HERNANDEZ

Contact Information

Contractor Courteous Construction Co Inc; Lic. No.: 567324-B P O BOX 9287      GLENDALE, CA 91226
Engineer Rezazadeh,, Mehdi; Lic. No.: C49626 P O BOX 98      DANVILLE, CA 94526

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/26/2020 Partial Inspection FRED WOHLFARTH
Wood Frame 3/5/2020 Corrections Issued FRED WOHLFARTH
Deputy Steel/Welding 3/16/2020 Conditional Approval MARK FERRARI
Floor/Roof Diaphrgm/Shear Wall 3/26/2020 Approved JONATHAN QUACH
Footing/Foundation/Slab 3/26/2020 Approved JONATHAN QUACH
Structural Steel Frame 3/26/2020 Approved JONATHAN QUACH
Deputy Reinf. Concrete 3/27/2020 Conditional Approval MARK FERRARI
Interior/Exterior Lathing 4/3/2020 Corrections Issued MARK FERRARI
Interior/Exterior Lathing 4/8/2020 Conditional Approval FELIX CEBALLOS
Final 4/27/2020 Partial Inspection FELIX CEBALLOS
SGSOV-Seismic Gas S/O Valve 4/27/2020 SGSOV Not Ready FELIX CEBALLOS
Smoke Detectors 4/27/2020 Approved FELIX CEBALLOS
Final 6/17/2020 OK for CofC FELIX CEBALLOS
SGSOV-Seismic Gas S/O Valve 6/17/2020 SGSOV Approved FELIX CEBALLOS