1345 N LAS PALMAS AVE 90028
Certificate Information: 1345 N LAS PALMAS AVE 90028
- Application / Permit
- 19016-10000-36005
- Plan Check / Job No.
- B19LA23765
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LABC CHAPTER 93. INSTALL STEEL CANTILEVER COLUMNS.
- Permit Issued
- Issued on 8/3/2020
- Issuing Office
- Current Status
- CofC Issued on 12/16/2020
Permit Application Status History
| Submitted | 11/15/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/4/2019 | MANUEL MONTUFAR |
| Corrections Issued | 12/10/2019 | MANUEL MONTUFAR |
| Quality Review Completed | 12/15/2019 | HANS SANTIAGO |
| Plan Check Approved | 2/20/2020 | MANUEL MONTUFAR |
| Issued | 8/3/2020 | APPLICANT |
| OK for CofC | 12/15/2020 | JONATHAN QUACH |
| CofC Issued | 12/16/2020 | ERNESTO CORRAL |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 2/5/2020 | MELISSA JONES |
| Redevelopment Project Area | Cleared | 2/10/2020 | GRACIELA ACOSTA |
| Tenant Habitability Plan | Cleared | 7/30/2020 | PHILLIP MUNGUIA |
Contact Information
| Contractor | Mercury Construction Inc; Lic. No.: 1004692-B | 3401 NORTH MISSION ROAD #1 LOS ANGELES, CA 90031 |
| Engineer | Puliyadi,, Senthilnath Surendran; Lic. No.: NA71630 | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/17/2020 | Approved | MARK FERRARI |
| Wood Frame | 9/9/2020 | Partial Approval | MARK FERRARI |
| Deputy Drilled-In Anchors | 9/28/2020 | Conditional Approval | MARK FERRARI |
| Deputy Drilled-In Anchors | 10/6/2020 | Conditional Approval | JONATHAN QUACH |
| Deputy Steel/Welding | 10/6/2020 | Conditional Approval | JONATHAN QUACH |
| Footing/Foundation/Slab | 10/7/2020 | Not Ready for Inspection | JONATHAN QUACH |
| Wood Frame | 10/7/2020 | Not Ready for Inspection | JONATHAN QUACH |
| Footing/Foundation/Slab | 10/9/2020 | Approved | JONATHAN QUACH |
| Structural Steel Frame | 10/9/2020 | Partial Approval | JONATHAN QUACH |
| Wood Frame | 10/9/2020 | Partial Approval | JONATHAN QUACH |
| Deputy Reinf. Concrete | 10/14/2020 | Conditional Approval | JONATHAN QUACH |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2020 | Approved | RUSSELL BONVOULOIR |
| Wood Frame | 10/19/2020 | Approved | RUSSELL BONVOULOIR |
| Drywall Nailing | 10/28/2020 | Not Ready for Inspection | JONATHAN QUACH |
| Interior/Exterior Lathing | 10/28/2020 | Not Ready for Inspection | JONATHAN QUACH |
| Interior/Exterior Lathing | 11/6/2020 | Partial Approval | JONATHAN QUACH |
| Final | 12/7/2020 | Not Ready for Inspection | JONATHAN QUACH |
| SGSOV-Seismic Gas S/O Valve | 12/7/2020 | SGSOV Not Ready | JONATHAN QUACH |
| Smoke Detectors | 12/7/2020 | Approved | JONATHAN QUACH |
| Final | 12/15/2020 | OK for CofC | JONATHAN QUACH |
| SGSOV-Seismic Gas S/O Valve | 12/15/2020 | SGSOV Approved | JONATHAN QUACH |