9851 S ALAMEDA ST 90002

Certificate Information: 9851 S ALAMEDA ST 90002

Application / Permit
19016-10000-35884
Plan Check / Job No.
B19LA23703
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Beauty Shop or Parlor
Work Description
CHANGE OF USE FROM RETAIL TO BEAUTY SALON -TENANT IMPROVEMENT FOR NAIL SPA (21' X 64') 1ST TENANT
Permit Issued
Issued on 2/13/2020
Issuing Office
Metro
Current Status
CofO Issued on 11/24/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/6/2019 APPLICANT
Assigned to Plan Check Engineer 11/14/2019 SAM CHANG
Corrections Issued 11/19/2019 SAM CHANG
Disabled Access Plans Picked Up 11/22/2019 APPLICANT
Green Plans Picked Up 11/22/2019 APPLICANT
Quality Review Completed 11/23/2019 STANLEY RAAP
Building Plans Picked Up 1/14/2020 APPLICANT
Applicant returned to address corrections 2/7/2020 SAM CHANG
Plan Check Approved 2/13/2020 SAM CHANG
Issued 2/13/2020 LADBS
CofO in Progress 11/14/2020 LEOPOLDO MENDOZA
CofO in Progress 11/14/2020 LEOPOLDO MENDOZA
Permit Finaled 11/24/2020 DAVID TSAU
CofO Issued 11/24/2020 DAVID TSAU
Permit Finaled 11/24/2020 DAVID TSAU

Permit Application Clearance Information

DAS Clearance Cleared 12/12/2019 WAI LAU
Green Code Cleared 12/12/2019 VIVIAN LAO
City owned building/parcel Cleared 1/30/2020 HAROOT AVANESIAN
Eng Process Fee Ord 176,300 Cleared 1/30/2020 JEANETTE VONG
Sewer availability Cleared 1/30/2020 JEANETTE VONG
ZA Case Cleared 2/7/2020 JOE LUCKEY
Specific Plan Cleared 2/10/2020 JEANALEE OBERGFELL
ZI Cleared 2/10/2020 JEANALEE OBERGFELL

Contact Information

Contractor Pham Calvin; Lic. No.: 819271-B 13345 WYNANT DRIVE      GARDEN GROVE, CA 92844
Engineer Inman,, Donald J; Lic. No.: C11888 5131 FOX HILLS AVENUE      BUENA PARK, CA 90621

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/24/2020 Approved LEOPOLDO MENDOZA
Deputy Drilled-In Anchors 3/25/2020 Conditional Approval DANIEL COLLINS
Light Gage Steel Frame 6/15/2020 Corrections Issued LEOPOLDO MENDOZA
Light Gage Steel Frame 7/1/2020 Not Ready for Inspection LEOPOLDO MENDOZA
Green Building Rough 8/6/2020 Not Ready for Inspection LEOPOLDO MENDOZA
Light Gage Steel Frame 8/6/2020 Approved LEOPOLDO MENDOZA
T-Bar Ceiling 8/6/2020 Approved LEOPOLDO MENDOZA
Wood Frame 8/6/2020 Not Ready for Inspection LEOPOLDO MENDOZA
Drywall Nailing 8/14/2020 Partial Approval LEOPOLDO MENDOZA
Final 10/2/2020 Not Ready for Inspection LEOPOLDO MENDOZA
Green Building Final 10/2/2020 Not Ready for Inspection LEOPOLDO MENDOZA
Green Building Rough 10/2/2020 Approved LEOPOLDO MENDOZA
SGSOV-Seismic Gas S/O Valve 10/2/2020 SGSOV No Gas LEOPOLDO MENDOZA
Smoke Detectors 10/2/2020 Not Ready for Inspection LEOPOLDO MENDOZA
Wood Frame 10/2/2020 Approved LEOPOLDO MENDOZA
Final 10/30/2020 Not Ready for Inspection LEOPOLDO MENDOZA
Green Building Final 10/30/2020 Not Ready for Inspection LEOPOLDO MENDOZA
Smoke Detectors 10/30/2020 Approved LEOPOLDO MENDOZA
Final 11/5/2020 OK to Issue CofO LEOPOLDO MENDOZA
Green Building Final 11/5/2020 Approved LEOPOLDO MENDOZA