1645 W ROCKWOOD ST 90026

Certificate Information: 1645 W ROCKWOOD ST 90026

Application / Permit
19016-10000-35835
Plan Check / Job No.
B19LA23665
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Soft-Story seismic retrofit per LABC Chapter 93: INSTALL (2) STEEL CANTILEVER COLUMNS.
Permit Issued
Issued on 5/15/2020
Issuing Office
Current Status
CofC Issued on 7/15/2021

Permit Application Status History

Submitted 12/2/2019 APPLICANT
Assigned to Plan Check Engineer 12/18/2019 DANIEL YIP
Corrections Issued 12/23/2019 DANIEL YIP
Quality Review Completed 12/25/2019 HANS SANTIAGO
Plan Check Approved 2/21/2020 DANIEL YIP
Issued 5/15/2020 APPLICANT
OK for CofC 6/30/2021 MARK FERRARI
CofC Issued 7/15/2021 WINSTON DUNNING

Permit Application Clearance Information

Housing rent stabilization Cleared 4/22/2020 MICHAEL GREGERSON

Contact Information

Engineer Puliyadi,, Senthilnath Surendran; Lic. No.: C71630 114 SHADOWHILL CIRCLE      SAN RAMON, CA 94583
Engineer Puliyadi,, Senthilnath Surendran; Lic. No.: NA71630       ,

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/20/2020 No Access for Inspection MARK FERRARI
Pre-Inspection 5/29/2020 Approved DARRYL ARNOLD
Excavation/Setback/Form/Re-Bar 6/17/2020 Partial Approval MARK FERRARI
Excavation/Setback/Form/Re-Bar 9/1/2020 Approved DANIEL COLLINS
Floor/Roof Diaphrgm/Shear Wall 10/20/2020 Approved DARRYL ARNOLD
Final 11/19/2020 No Access for Inspection MARK FERRARI
METHANE-Final 11/19/2020 No Access for Inspection MARK FERRARI
SGSOV-Seismic Gas S/O Valve 11/19/2020 SGSOV Not Ready MARK FERRARI
Smoke Detectors 11/19/2020 No Access for Inspection MARK FERRARI
Final 11/25/2020 Corrections Issued MARK FERRARI
METHANE-Final 11/25/2020 Approved MARK FERRARI
SGSOV-Seismic Gas S/O Valve 11/25/2020 SGSOV Not Ready MARK FERRARI
Smoke Detectors 11/25/2020 Not Ready for Inspection MARK FERRARI
Final 12/15/2020 Not Ready for Inspection MARK FERRARI
SGSOV-Seismic Gas S/O Valve 12/15/2020 SGSOV Not Ready MARK FERRARI
Smoke Detectors 12/15/2020 Not Ready for Inspection MARK FERRARI
Final 3/25/2021 Not Ready for Inspection DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 3/25/2021 SGSOV Not Ready DARRYL ARNOLD
Smoke Detectors 3/25/2021 Approved DARRYL ARNOLD
Final 6/30/2021 OK for CofC MARK FERRARI
SGSOV-Seismic Gas S/O Valve 6/30/2021 SGSOV Approved MARK FERRARI