907 S HOLT AVE 90035
Certificate Information: 907 S HOLT AVE 90035
- Application / Permit
- 19016-10000-35788
- Plan Check / Job No.
- B19LA23635
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH 93. INSTALL TWO (2) NEW SCCS
- Permit Issued
- Issued on 12/15/2021
- Issuing Office
- Current Status
- CofC Issued on 4/13/2022
Permit Application Status History
| Submitted | 11/6/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/4/2019 | BIDYUT RATH |
| Corrections Issued | 12/16/2019 | BIDYUT RATH |
| Quality Review Completed | 12/18/2019 | HANS SANTIAGO |
| Plan Check Approved | 5/20/2020 | VARAND SARKISIAN |
| Issued | 12/15/2021 | APPLICANT |
| Building Plans Picked Up | 12/16/2021 | APPLICANT |
| OK for CofC | 4/12/2022 | DARRYL ARNOLD |
| CofC Issued | 4/13/2022 | WINSTON DUNNING |
Permit Application Clearance Information
| Construction within easement | Cleared | 1/7/2020 | TORI CHEN |
| Housing rent stabilization | Cleared | 11/24/2021 | PHILLIP MUNGUIA |
Contact Information
| Contractor | Cal Retrofit; Lic. No.: 1022167-B | 19528 VENTURA BLVD #300 TARZANA, CA 91356 |
| Engineer | Zohrevand,, Pedram; Lic. No.: C82328 | 21201 KITTRIDGE ST APT 9105 WOODLAND HILLS, CA 91303 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/27/2021 | Approved | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 2/8/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 2/8/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Steel/Welding | 2/8/2022 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 2/15/2022 | Conditional Approval | DARRYL ARNOLD |
| Structural Steel Frame | 2/15/2022 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 2/15/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 2/17/2022 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 2/24/2022 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 3/22/2022 | Conditional Approval | DARRYL ARNOLD |
| Final | 4/12/2022 | OK for CofC | DARRYL ARNOLD |
| METHANE-Final | 4/12/2022 | Approved | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 4/12/2022 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 4/12/2022 | Approved | DARRYL ARNOLD |