2506 S MAIN ST 90007
Certificate Information: 2506 S MAIN ST 90007
- Application / Permit
- 19016-10000-35761
- Plan Check / Job No.
- B19LA23622
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (12) Welding acetylene or electric
- Work Description
- Change of use from retail/auto repair garage/used car sale/tire shop to weel/welding fabrication. "COMPLY WITH DEPARTMENT ORDER effective date 04/03/2017. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 6/17/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/9/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/5/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/14/2019 | SERGIO GUTIERREZ |
| Corrections Issued | 11/18/2019 | SERGIO GUTIERREZ |
| Quality Review Completed | 12/2/2019 | KESETE HAREGOT |
| Building Plans Picked Up | 12/4/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 1/16/2020 | APPLICANT |
| Applicant returned to address corrections | 2/12/2020 | SERGIO GUTIERREZ |
| Plan Check Approved | 3/4/2020 | SERGIO GUTIERREZ |
| Issued | 6/17/2020 | LADBS |
| CofO in Progress | 4/9/2021 | ERNESTO CORRAL |
| CofO Issued | 4/9/2021 | ERNESTO CORRAL |
| Permit Finaled | 4/9/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| DAS Clearance | Cleared | 1/28/2020 | SERGIO GUTIERREZ |
| Historic Resource Verification | Cleared | 1/28/2020 | GISELLE CORELLA |
| Redevelopment Project Area | Cleared | 1/28/2020 | GISELLE CORELLA |
| Community Plan Implem. Overlay | Cleared | 3/2/2020 | HELEN JADALI |
Contact Information
| Contractor | Baksh Construction Inc; Lic. No.: 910533-B | 4 HILLCREST MANOR ROLLING HILLS ESTATES, CA 90274 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 1/29/2021 | Not Ready for Inspection | LANNY MERRICK |
| METHANE-Final | 1/29/2021 | Not Ready for Inspection | LANNY MERRICK |
| Final | 2/19/2021 | Conditional Approval | LANNY MERRICK |
| METHANE-Final | 2/19/2021 | Approved | LANNY MERRICK |