590 S BURLINGAME AVE 90049

Certificate Information: 590 S BURLINGAME AVE 90049

Application / Permit
19016-10000-35757
Plan Check / Job No.
B19LA23616
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
Remodel of (E) café to provide additional storage, additional exterior seating, walk-in cooler, new equipment, fixtures, and finishes. 390 sf of existing open patio to remain. 2290 sf of interior space total to be remodeled. Add outdoor dining 495 sf. Reframe ceiling add roof top equipment 1 of 2
Permit Issued
Issued on 3/3/2020
Issuing Office
Metro
Current Status
Permit Finaled on 1/3/2023

Permit Application Status History

Submitted 11/6/2019 APPLICANT
Disabled Access Plans Picked Up 11/13/2019 APPLICANT
Assigned to Plan Check Engineer 11/14/2019 ZAW HAN
Corrections Issued 11/18/2019 ZAW HAN
Quality Review Completed 12/3/2019 BILL STUTSMAN
Building Plans Picked Up 12/3/2019 APPLICANT
Applicant returned to address corrections 2/11/2020 ZAW HAN
Plan Check Approved 3/2/2020 ZAW HAN
Issued 3/3/2020 LADBS
Permit Finaled 1/3/2023 SORIN CIRSTOIU

Permit Application Clearance Information

Comm Cor/Mini-Mall Cleared 12/5/2019 ANNA VAN
Eng Process Fee Ord 176,300 Cleared 12/18/2019 ERIK BEASLEY
Sewer availability Cleared 12/18/2019 ERIK BEASLEY
Specific Plan Cleared 12/26/2019 KIT AWAKUNI
ZA Case Cleared 12/26/2019 KIT AWAKUNI
Fire Marshall Fire Life Safety Cleared 1/29/2020 VIDAL GARCIA
Food Service Establishment Cleared 2/6/2020 KENNETH BROWNE
DAS Clearance Cleared 2/10/2020 SHINE LIN
Food establishment approval Cleared 2/11/2020 LACDHS APPROVED

Contact Information

Architect Fleetwood,, Thomas Hunter; Lic. No.: C31676 1275 E 6TH STREET SUITE 202      LOS ANGELES, CA 90021
Contractor Sarlan Builders Inc; Lic. No.: 387668-B 9903 SANTA MONICA BLVD #269      BEVERLY HILLS, CA 90212
Engineer Amoroso,, Gregory Michael; Lic. No.: L8771 24269 PALO VERDE DR      VALENCIA, CA 91354
Engineer Tuchscher,, James Todd; Lic. No.: C77649 5503 E 2ND ST      LONG BEACH, CA 90803

Inspector Information

CASIMIR BRITTON, (310) 914-3913 Office Hours: 7:00-8:00 AM MON-FRI
SHAVONNE ESPINOZA, (310) 914-3913 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/29/2020 Conditional Approval JOHN DODGE
Excavation/Setback/Form/Re-Bar 4/30/2020 Approved JOHN DODGE
Floor/Roof Diaphrgm/Shear Wall 5/13/2020 Corrections Issued PAUL DAVIDSON
Wood Frame 5/14/2020 Not Ready for Inspection JOHN DODGE
Wood Frame 5/19/2020 Partial Approval PAUL DAVIDSON
Pre-Inspection 5/21/2020 Approved JEFF BYTHEWAY
Deputy Drilled-In Anchors 5/26/2020 Conditional Approval PAUL DAVIDSON
Drywall Nailing 6/11/2020 Not Ready for Inspection JOHN DODGE
Drywall Nailing 6/22/2020 Partial Approval JOHN DODGE
Special/Order Compliance 6/24/2020 Approved JOHN DODGE
Footing/Foundation/Slab 6/29/2020 Conditional Approval JOHN DODGE
Excavation/Setback/Form/Re-Bar 7/14/2020 Partial Approval JOHN DODGE
Special/Order Compliance 7/27/2020 Approved JOHN DODGE
Light Gage Steel Frame 8/19/2020 Partial Inspection JOHN DODGE
Footing/Foundation/Slab 9/2/2020 Partial Inspection JOHN DODGE
Drywall Nailing 9/3/2020 Partial Approval JOHN DODGE
Footing/Foundation/Slab 9/8/2020 Approved JOHN DODGE
Light Gage Steel Frame 9/8/2020 Not Ready for Inspection JOHN DODGE
Drywall Nailing 9/9/2020 Partial Approval JOHN DODGE
Drywall Nailing 9/14/2020 Not Ready for Inspection JOHN DODGE
Light Gage Steel Frame 9/14/2020 Conditional Approval JOHN DODGE
Drywall Nailing 9/16/2020 Partial Approval JOHN DODGE
Light Gage Steel Frame 9/16/2020 Partial Approval JOHN DODGE
Light Gage Steel Frame 9/23/2020 Partial Approval JOHN DODGE
Light Gage Steel Frame 9/29/2020 Partial Approval JOHN DODGE
Drywall Nailing 10/2/2020 Partial Approval JOHN DODGE
T-Bar Ceiling 10/2/2020 Not Ready for Inspection JOHN DODGE
Drywall Nailing 10/5/2020 Not Ready for Inspection JOHN DODGE
Drywall Nailing 10/6/2020 Partial Approval JOHN DODGE
Special/Order Compliance 10/9/2020 Partial Inspection JOHN DODGE
Interior/Exterior Lathing 10/13/2020 Partial Approval JOHN DODGE
Special/Order Compliance 10/27/2020 Approved JOHN DODGE
Special/Order Compliance 11/23/2020 Approved JOHN DODGE
Special/Order Compliance 11/30/2020 No Access for Inspection JOHN DODGE
Wood Frame 11/30/2020 No Access for Inspection JOHN DODGE
Light Gage Steel Frame 12/1/2020 Approved JOHN DODGE
Pre-Inspection 12/4/2020 Approved JOHN DODGE
Special/Order Compliance 12/4/2020 Partial Inspection JOHN DODGE
Wood Frame 12/4/2020 Not Ready for Inspection JOHN DODGE
Insulation 12/15/2020 Approved JOHN DODGE
Drywall Nailing 12/21/2020 Partial Approval JOHN DODGE
Light Gage Steel Frame 12/22/2020 Partial Approval JOHN DODGE
Wood Frame 12/22/2020 Partial Approval JOHN DODGE
Drywall Nailing 12/24/2020 Approved ALAN NOVAK
Interior/Exterior Lathing 12/31/2020 Approved JOHN DODGE
Light Gage Steel Frame 1/7/2021 Partial Approval JOHN DODGE
Special/Order Compliance 1/15/2021 Approved JOHN DODGE
Drywall Nailing 1/28/2021 Approved JOHN DODGE
Special/Order Compliance 3/4/2021 Approved JOHN DODGE
Pre-Inspection 4/1/2021 Not Ready for Inspection LEOPOLDO MENDOZA
Final 4/5/2021 Partial Inspection JOHN DODGE
SGSOV-Seismic Gas S/O Valve 4/5/2021 SGSOV Not Ready JOHN DODGE
Smoke Detectors 4/5/2021 Approved JOHN DODGE
Final 4/26/2021 Conditional Approval JOHN DODGE
SGSOV-Seismic Gas S/O Valve 4/26/2021 SGSOV Approved JOHN DODGE
Final 1/3/2023 Permit Finaled SORIN CIRSTOIU