210 E OLYMPIC BLVD 90015
Certificate Information: 210 E OLYMPIC BLVD 90015
- Application / Permit
- 19016-10000-35614
- Plan Check / Job No.
- B19LA23523
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- TENANT IMPROVEMENT OF THE 1ST LEVEL OF A MULTI STORY OFFICE & RETAIL BUILDING. PORTION OF WORK TO INCLUDE NEW 30' X 12' TRELLIS @ THE ENTRY OF THE BUILDING. PORTION OF SLAB ON THE SECOND FLOOR TO BE INFILLED
- Permit Issued
- Issued on 5/8/2020
- Issuing Office
- Current Status
- Permit Finaled on 5/18/2022
Permit Application Status History
| Submitted | 11/5/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2019 | MICHAEL PEREZ |
| Corrections Issued | 11/13/2019 | MICHAEL PEREZ |
| Green Plans Picked Up | 11/19/2019 | APPLICANT |
| Quality Review Completed | 11/26/2019 | JOSE RODRIGUEZ |
| Building Plans Picked Up | 12/5/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 12/11/2019 | APPLICANT |
| Plan Check Approved | 2/20/2020 | MICHAEL PEREZ |
| Issued | 5/8/2020 | APPLICANT |
| Permit Finaled | 5/18/2022 | TIMOTHY BUXTON |
Permit Application Clearance Information
| "D" conditions | Cleared | 1/31/2020 | LATANYA ROUX |
| CPC | Cleared | 1/31/2020 | LATANYA ROUX |
| Redevelopment Project Area | Cleared | 1/31/2020 | GRACIELA ACOSTA |
| Green Code | Cleared | 2/12/2020 | VIVIAN LAO |
| DAS Clearance | Cleared | 2/20/2020 | MICHAEL PEREZ |
Contact Information
| Architect | Liljegren,, Karin J; Lic. No.: C28158 | 600 CRANE BLVD LOS ANGELES, CA 90065 |
| Contractor | Severo Adrien Vincent; Lic. No.: 891039-B | 3579 E FOOTHILL BLVD STE 426 PASADENA, CA 91107 |
| Engineer | Fischer,, Kurt Mark; Lic. No.: S5432 | PO BOX 809 POWAY, CA 92074 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 5/26/2020 | Corrections Issued | KATY RAMIREZ |
| Light Gage Steel Frame | 5/26/2020 | Partial Inspection | KATY RAMIREZ |
| Drywall Nailing | 7/2/2020 | Partial Approval | KATY RAMIREZ |
| Footing/Foundation/Slab | 7/20/2020 | Partial Approval | KATY RAMIREZ |
| Deputy Reinf. Concrete | 7/22/2020 | Conditional Approval | DANIEL COLLINS |
| Drywall Nailing | 8/4/2020 | Corrections Issued | KATY RAMIREZ |
| Deputy Drilled-In Anchors | 9/3/2020 | Conditional Approval | DANIEL COLLINS |
| Footing/Foundation/Slab | 9/11/2020 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 9/11/2020 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 3/5/2021 | Corrections Issued | KATY RAMIREZ |
| Final | 4/22/2022 | Not Ready for Inspection | TIMOTHY BUXTON |
| Final | 4/28/2022 | Partial Inspection | TIMOTHY BUXTON |
| Green Building Final | 4/28/2022 | Approved | TIMOTHY BUXTON |
| SGSOV-Seismic Gas S/O Valve | 4/28/2022 | SGSOV No Gas | TIMOTHY BUXTON |
| Smoke Detectors | 4/28/2022 | Approved | TIMOTHY BUXTON |
| Final | 5/18/2022 | Permit Finaled | TIMOTHY BUXTON |