3819 W SUNSET DR 90027

Certificate Information: 3819 W SUNSET DR 90027

Application / Permit
19016-10000-35443
Plan Check / Job No.
B19LA23423
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL OF EXISTING SINGLE FAMILY DWELLING. CONVERT BASEMENT TO HABITABLE SPACE. NEW INTERIOR SPIRAL STAIRS PER STANDARD PLAN.**GREEN FEES CAPTURED UNDER SUBMITTAL 2**
Permit Issued
Issued on 7/6/2020
Issuing Office
Current Status
CofO Issued on 5/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/4/2019 APPLICANT
Assigned to Plan Check Engineer 11/7/2019 PRANITA SHAH
Corrections Issued 11/19/2019 PRANITA SHAH
Quality Review Completed 12/4/2019 TU HUA
Building Plans Picked Up 12/20/2019 APPLICANT
Applicant returned to address corrections 3/17/2020 PRANITA SHAH
Applicant returned to address corrections 4/6/2020 PRANITA SHAH
Applicant returned to address corrections 5/15/2020 PRANITA SHAH
Green Plans Picked Up 6/16/2020 APPLICANT
Plan Check Approved 6/30/2020 PRANITA SHAH
Issued 7/6/2020 APPLICANT
CofO in Progress 5/6/2024 ENRIQUE MIRELES
CofO Issued 5/16/2024 DEROLD HAUFF
Permit Finaled 5/16/2024 DEROLD HAUFF

Permit Application Clearance Information

Distance to fire station Cleared 1/31/2020 ROBERT DUFF
Eng Process Fee Ord 176,300 Cleared 1/31/2020 ERIK BEASLEY
Hydrant and Access approval Cleared 1/31/2020 ROBERT DUFF
Sewer availability Cleared 1/31/2020 ERIK BEASLEY
Green Code Cleared 3/4/2020 KHEDER ALRAZAA
Grading Pre-Inspection Cleared 6/30/2020 PRANITA SHAH

Contact Information

Contractor Progressive Environmental Concepts; Lic. No.: 543710-B 9049 LEMORAN AVENUE      DOWNEY, CA 90240
Engineer Benavides,, Jose Alexander; Lic. No.: C72968 644 N POPLAR ST UNIT B      ORANGE, CA 92868

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 6/23/2021 Corrections Issued JOSEPH MCGARRY
Special/Order Compliance 6/30/2021 Not Ready for Inspection JOSEPH MCGARRY
Special/Order Compliance 7/8/2021 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 8/31/2023 Approved JEFFREY MEAD
Final 8/31/2023 Corrections Issued JEFFREY MEAD
Green Building Final 8/31/2023 Approved JEFFREY MEAD
Green Building Rough 8/31/2023 Approved JEFFREY MEAD
HVAC-Final 8/31/2023 Approved JEFFREY MEAD
PLUMBING-Final 8/31/2023 Approved JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 8/31/2023 SGSOV Approved JEFFREY MEAD
Smoke Detectors 8/31/2023 Approved JEFFREY MEAD
Final 4/29/2024 OK to Issue CofO ENRIQUE MIRELES