20209 W RINALDI ST 91326
Certificate Information: 20209 W RINALDI ST 91326
- Application / Permit
- 19016-10000-35321
- Plan Check / Job No.
- B19LA23353
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- NEW COMMERCIAL ROOFTOP SOLAR SYSTEM.
- Permit Issued
- Issued on 3/6/2020
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 10/1/2020
Permit Application Status History
| Submitted | 11/1/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/7/2019 | KEVIN MORALES |
| Corrections Issued | 11/14/2019 | KEVIN MORALES |
| Quality Review Completed | 11/17/2019 | YOUNG KIM |
| Building Plans Picked Up | 11/18/2019 | APPLICANT |
| Plan Check Approved | 2/12/2020 | KEVIN MORALES |
| Issued | 3/6/2020 | LADBS |
| Permit Finaled | 9/30/2020 | JEFFREY FULTON |
Permit Application Clearance Information
| "D" conditions | Cleared | 11/20/2019 | RICHARD REASER |
| Specific Plan | Cleared | 1/15/2020 | SARAH GOLDMAN |
| Miscellaneous | Cleared | 2/12/2020 | WILLIAM JOHNS |
Contact Information
| Contractor | Sunpower Corporation Systems; Lic. No.: 890895-C10 | 1414 HARBOUR WAY S SUITE 1901 RICHMOND, CA 94804 |
| Engineer | Scott,, Paul Gregory; Lic. No.: S3325 | 1215 RIO SALADO PKWY STE 200 TEMPE, AZ 85281 |
| Engineer | Ward,, Leon David; Lic. No.: C19459 | 2565 N HOLLISTON AVE ALTADENA, CA 91001 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/26/2020 | Partial Inspection | JEFFREY FULTON |
| Deputy Wood Construction | 8/28/2020 | Conditional Approval | JEFFREY FULTON |
| Deputy Wood Construction | 8/31/2020 | Conditional Approval | JEFFREY FULTON |
| Deputy Wood Construction | 9/1/2020 | Conditional Approval | JEFFREY FULTON |
| Final | 9/14/2020 | Not Ready for Inspection | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 9/14/2020 | SGSOV Not Ready | JEFFREY FULTON |
| Smoke Detectors | 9/14/2020 | Not Ready for Inspection | JEFFREY FULTON |
| Final | 9/30/2020 | Permit Finaled | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 9/30/2020 | SGSOV Approved | JEFFREY FULTON |
| Smoke Detectors | 9/30/2020 | Approved | JEFFREY FULTON |