2030 S CABRILLO AVE 90731
Certificate Information: 2030 S CABRILLO AVE 90731
- Application / Permit
- 19016-10000-35294
- Plan Check / Job No.
- B19LA23331
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH. 93. BY INSTALLING 2 (N) STEEL MOMENT FRAME
- Permit Issued
- Issued on 5/9/2022
- Issuing Office
- Metro
- Current Status
- Issued on 5/9/2022
Permit Application Status History
| Submitted | 11/1/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/4/2019 | JESSE VIDUYA |
| Corrections Issued | 12/10/2019 | JESSE VIDUYA |
| Quality Review Completed | 12/16/2019 | SAI KHUM |
| Building Plans Picked Up | 1/6/2020 | APPLICANT |
| Applicant returned to address corrections | 4/28/2020 | JESSE VIDUYA |
| Applicant returned to address corrections | 8/5/2020 | JESSE VIDUYA |
| Plan Check Approved | 8/6/2020 | JESSE VIDUYA |
| Issued | 5/9/2022 | APPLICANT |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 8/24/2020 | MICHAEL GREGERSON |
Contact Information
| Contractor | Los Angeles Retrofit & Construction Inc; Lic. No.: 1023060-B | 18075 VENTURA BLVD STE #101 ENCINO, CA 91316 |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVENUE LONG BEACH, CA 90813 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/22/2022 | Partial Inspection | DAVID TSAU |
| Deputy Drilled-In Anchors | 8/10/2022 | Conditional Approval | DAVID TSAU |
| Footing/Foundation/Slab | 8/15/2022 | Not Ready for Inspection | JOEY BUCHANAN |
| Structural Steel Frame | 8/15/2022 | Not Ready for Inspection | JOEY BUCHANAN |
| Wood Frame | 8/15/2022 | Not Ready for Inspection | JOEY BUCHANAN |
| Footing/Foundation/Slab | 8/18/2022 | Approved | JOEY BUCHANAN |
| Structural Steel Frame | 8/18/2022 | Approved | JOEY BUCHANAN |
| Wood Frame | 8/18/2022 | Not Ready for Inspection | JOEY BUCHANAN |
| Wood Frame | 8/24/2022 | Approved | DAVID TSAU |
| Insulation | 9/1/2022 | Approved | DAVID TSAU |
| Interior/Exterior Lathing | 9/15/2022 | Approved | JOEY BUCHANAN |
| Final | 11/2/2022 | Not Ready for Inspection | JOEY BUCHANAN |
| SGSOV-Seismic Gas S/O Valve | 11/2/2022 | SGSOV Not Ready | JOEY BUCHANAN |
| Smoke Detectors | 11/2/2022 | Approved | JOEY BUCHANAN |
| Final | 3/12/2025 | Corrections Issued | MICHAEL PETRUSKO |
| SGSOV-Seismic Gas S/O Valve | 3/12/2025 | Corrections Issued | MICHAEL PETRUSKO |