4716 W LOMITA ST 90019
Certificate Information: 4716 W LOMITA ST 90019
- Application / Permit
- 19016-10000-35257
- Plan Check / Job No.
- B19LA23296
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CHAPTER 93 INSTALL (3) SCCS.
- Permit Issued
- Issued on 5/20/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 4/20/2021
Permit Application Status History
| Submitted | 11/1/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/4/2019 | DANIEL YIP |
| Corrections Issued | 12/9/2019 | DANIEL YIP |
| Quality Review Completed | 12/16/2019 | SAI KHUM |
| Building Plans Picked Up | 12/18/2019 | APPLICANT |
| Plan Check Approved | 1/14/2020 | DANIEL YIP |
| Issued | 5/20/2020 | LADBS |
| OK for CofC | 4/13/2021 | DARRYL ARNOLD |
| OK for CofC | 4/13/2021 | DARRYL ARNOLD |
| CofC Issued | 4/20/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Construction near power lines | Cleared | 1/2/2020 | OSCAR CASTRO |
| Construction within easement | Cleared | 1/2/2020 | OSCAR CASTRO |
| Housing rent stabilization | Cleared | 4/22/2020 | MICHAEL GREGERSON |
Contact Information
| Contractor | Ararat Construction Co Inc; Lic. No.: 471822-B | 6131 SAN VICENTE BLVD LOS ANGELES, CA 90048 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/26/2020 | Approved | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 6/8/2020 | Conditional Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 6/8/2020 | Conditional Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 7/16/2020 | Conditional Approval | DARRYL ARNOLD |
| Excavation/Setback/Form/Re-Bar | 7/16/2020 | Partial Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 7/16/2020 | Partial Inspection | DARRYL ARNOLD |
| Wood Frame | 7/16/2020 | Approved | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 7/17/2020 | Conditional Approval | MARK FERRARI |
| Wood Frame | 7/29/2020 | Approved | DARRYL ARNOLD |
| Wood Frame | 8/7/2020 | Approved | DARRYL ARNOLD |
| Final | 8/20/2020 | Not Ready for Inspection | DARRYL ARNOLD |
| METHANE-Final | 8/20/2020 | Approved | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 8/20/2020 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 8/20/2020 | Approved | DARRYL ARNOLD |
| Final | 4/13/2021 | OK for CofC | DARRYL ARNOLD |